Thought there was talk of only going as far as Bletchley
There was a definite 'staging' of the work confusingly described in the most recent
CP5▸ enhancements plan (draft) back in December, but wiring Bletchley to Bedford was definitely in there somewhere:
Electrification (25kv AC overhead) of the route between Oxford and Bletchley
This scheme provides electrification of this section of the upgraded and reopened railway
from Oxford to Bedford. Electrification of the route between Oxford and Bletchley will be
undertaken in conjunction with the East West Rail project.
The difference is possibly that east of Bletchley all the work is to be done on a live railway that isn't having any other major upgrade work - so if there is stuff like bridge clearance work to be done it will take a bit longer as it will have to be fitted round operating services.
But there's also the point that if the main purpose of the electric spine is to allow traffic to flow Oxford to Bletchley to Bedford then northwards from Bedford - then that requires electrification of the
MML» , which will not be ready when EWR wiring gets as far as Bletchley, but of course the
WCML▸ is already wired north of Bletchley. What I'm suggesting is that wiring Bletchley to Bedford could be a dead end for a couple of years if done at the same time.
Paul