Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 19:48, 27th December 2024 |
Realtime Trains reporting
1W03 1818 Reading to Hereford - This service was cancelled due to a decision by the train operating company (TR)
1W36 1921 Reading to Worcester Foregate Street - This service was cancelled due to the planned train being replaced with a slower train (MS)
1W36 1921 Reading to Worcester Foregate Street - This service was cancelled due to the planned train being replaced with a slower train (MS)
whist JourneyCheck explains the 1921 Reading to Worcester Foregate Street cancellation as "due to a shortage of train crew"
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 11:40, 27th December 2024 |
Friday December 27
09:19 Reading to Great Malvern due 11:14 has been cancelled.
This is due to a fault on this train.
Last Updated:27/12/2024 10:00
12:18 Reading to Hereford due 14:45 has been cancelled.
This is due to a fault on this train.
Last Updated:27/12/2024 12:32
16:18 Reading to Great Malvern due 18:26 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:27/12/2024 04:18
23:30 Reading to Worcestershire Parkway Hl due 01:06 will be cancelled.
This is due to a shortage of train crew.
Last Updated:27/12/2024 10:34
11:57 Great Malvern to Reading due 13:57 will be cancelled.
This is due to a fault on this train.
Last Updated:27/12/2024 10:00
15:18 Hereford to Reading due 17:58 will be cancelled.
This is due to a fault on this train.
Last Updated:27/12/2024 12:32
19:04 Great Malvern to Reading due 21:02 will be cancelled.
This is due to a shortage of train crew.
Last Updated:27/12/2024 04:18
21:17 Worcester Foregate Street to Reading due 23:05 will be cancelled.
This is due to a shortage of train crew.
Last Updated:27/12/2024 09:58
This is due to a fault on this train.
Last Updated:27/12/2024 10:00
12:18 Reading to Hereford due 14:45 has been cancelled.
This is due to a fault on this train.
Last Updated:27/12/2024 12:32
16:18 Reading to Great Malvern due 18:26 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:27/12/2024 04:18
23:30 Reading to Worcestershire Parkway Hl due 01:06 will be cancelled.
This is due to a shortage of train crew.
Last Updated:27/12/2024 10:34
11:57 Great Malvern to Reading due 13:57 will be cancelled.
This is due to a fault on this train.
Last Updated:27/12/2024 10:00
15:18 Hereford to Reading due 17:58 will be cancelled.
This is due to a fault on this train.
Last Updated:27/12/2024 12:32
19:04 Great Malvern to Reading due 21:02 will be cancelled.
This is due to a shortage of train crew.
Last Updated:27/12/2024 04:18
21:17 Worcester Foregate Street to Reading due 23:05 will be cancelled.
This is due to a shortage of train crew.
Last Updated:27/12/2024 09:58
13:00 : updated.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 22:14, 24th December 2024 |
Well, the answer to my earlier question is
1W05 19:53 London Paddington to Hereford
Here's the latest score for this evening:
Up trains
1P05 15:18 Hereford to London Paddington (18:29) : Cancelled after Shrub Hill.
1P38 16:32 Great Malvern to London Paddington (19:29) : OK.
1P39 17:30 Worcester Foregate St to London Paddington (19:52) : OK
1P40 18:02 Foregate St to London Paddington (20:29 : cancelled throughout.
2E16 18:51 Evesham to Oxford : OK.
1P42 19:04 Great Malvern to London Paddington : cancelled due to an issue with the train crew (TG).
1P44 19:45 Great Malvern to Reading : cancelled due to late arrival of an inbound service (YI).
1P46 20:56 Worcester Foregate Street to Oxford : cancelled due to an issue with the train crew (TG).
Down trains
1W30 15:23 London Paddington to Foregate St : cancelled after Worcester Shrub Hill due to an issue with the train crew (TG).
1W31 15:52 London Paddington to Great Malvern (18:26) : cancelled due to an issue with the train crew (TG).
2E14 17:04 Didcot Parkway to Evesham : OK
1W33 16:58 London Paddington to Great Malvern (19:26) : cancelled due to unknown cause (ZW).
1W03 17:34 London Paddington to Hereford (20:25) : cancelled between Worcester Shrub Hill and Hereford due to an issue with the train crew (TG).
1W34 1757 London Paddington to Worcester Foregate Street : cancelled due to an issue with the train crew (TG).
1W36 1857 London Paddington to Great Malvern : cancelled due to an issue with the train crew (TG).
1W05 1953 London Paddington to Hereford : OK
1W41 2052 London Paddington to Worcester Shrub Hill : cancelled due to an issue with the train crew (TG).
1W43 2153 London Paddington to Worcester Shrub Hill : cancelled due to the planned cancellation (was not planned to operate) (PD).
1W45 2251 London Paddington to Worcestershire Parkway : cancelled due to the planned cancellation (was not planned to operate) (PD).
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 19:17, 24th December 2024 |
Cancellations to services between Oxford and Great Malvern
Due to a shortage of train crew between Oxford and Great Malvern fewer trains are able to run on all lines.
Train services running through these stations will be cancelled or revised. Disruption is expected until the end of the day.
Last Updated:24/12/2024 19:05
Due to a shortage of train crew between Oxford and Great Malvern fewer trains are able to run on all lines.
Train services running through these stations will be cancelled or revised. Disruption is expected until the end of the day.
Last Updated:24/12/2024 19:05
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 16:32, 24th December 2024 |
15:18 Hereford to London Paddington due 18:29 will be terminated at Worcester Shrub Hill.
It will no longer call at Worcestershire Parkway Hl, Pershore, Evesham, Honeybourne, Moreton-In-Marsh, Kingham, Charlbury, Hanborough, Oxford, Didcot Parkway, Reading and London Paddington.
This is due to a shortage of train crew
15:52 London Paddington to Great Malvern due 18:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 15:37
16:58 London Paddington to Great Malvern due 19:25 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 15:23
20:56 Worcester Foregate Street to Oxford due 22:21 will be cancelled.
This is due to a shortage of train crew.
It will no longer call at Worcestershire Parkway Hl, Pershore, Evesham, Honeybourne, Moreton-In-Marsh, Kingham, Charlbury, Hanborough, Oxford, Didcot Parkway, Reading and London Paddington.
This is due to a shortage of train crew
15:52 London Paddington to Great Malvern due 18:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 15:37
16:58 London Paddington to Great Malvern due 19:25 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 15:23
20:56 Worcester Foregate Street to Oxford due 22:21 will be cancelled.
This is due to a shortage of train crew.
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 15:54, 24th December 2024 |
15:18 Hereford to London Paddington due 18:29 will be terminated at Worcester Shrub Hill.
It will no longer call at Worcestershire Parkway Hl, Pershore, Evesham, Honeybourne, Moreton-In-Marsh, Kingham, Charlbury, Hanborough, Oxford, Didcot Parkway, Reading and London Paddington.
This is due to a shortage of train crew
15:52 London Paddington to Great Malvern due 18:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 15:37
16:58 London Paddington to Great Malvern due 19:25 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 15:23
20:56 Worcester Foregate Street to Oxford due 22:21 will be cancelled.
This is due to a shortage of train crew.
It will no longer call at Worcestershire Parkway Hl, Pershore, Evesham, Honeybourne, Moreton-In-Marsh, Kingham, Charlbury, Hanborough, Oxford, Didcot Parkway, Reading and London Paddington.
This is due to a shortage of train crew
15:52 London Paddington to Great Malvern due 18:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 15:37
16:58 London Paddington to Great Malvern due 19:25 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 15:23
20:56 Worcester Foregate Street to Oxford due 22:21 will be cancelled.
This is due to a shortage of train crew.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 10:37, 24th December 2024 |
Tuesday December 24
15:23 London Paddington to Worcester Foregate Street due 17:47 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/12/2024 08:19
15:52 London Paddington to Great Malvern due 18:26 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/12/2024 08:19
16:58 London Paddington to Great Malvern due 19:25 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:24/12/2024 08:57
17:34 London Paddington to Hereford due 20:25 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/12/2024 10:54
18:57 London Paddington to Great Malvern due 21:18 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 11:38
This is due to a shortage of train crew.
Last Updated:24/12/2024 08:19
15:52 London Paddington to Great Malvern due 18:26 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/12/2024 08:19
16:58 London Paddington to Great Malvern due 19:25 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:24/12/2024 08:57
17:34 London Paddington to Hereford due 20:25 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/12/2024 10:54
18:57 London Paddington to Great Malvern due 21:18 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 11:38
17:26 Worcester Foregate Street to London Paddington due 19:52 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:24/12/2024 10:01
18:02 Worcester Foregate Street to London Paddington due 20:29 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 11:16
19:04 Great Malvern to London Paddington due 21:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 12:39
This is due to a shortage of train crew.
Last Updated:24/12/2024 10:01
18:02 Worcester Foregate Street to London Paddington due 20:29 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 11:16
19:04 Great Malvern to London Paddington due 21:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/12/2024 12:39
12:55 : updated.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 10:21, 23rd December 2024 |
Monday December 23
After last night's cancellation of the positioning journey,
23/12/24 05:23 Hereford to London Paddington due 08:23 will be cancelled.
This is due to a broken down train earlier today.
Last Updated:22/12/2024 17:24
This is due to a broken down train earlier today.
Last Updated:22/12/2024 17:24
This was followed by a points failure between Evesham and Shrub Hill, so there's lots of late running.
1W11 0553 London Paddington to Great Malvern was held at Evesham (+55), arrived Worcester Shrub Hill +53 and was cancelled thereafter.
1W13 0650 London Paddington to Great Malvern was held at Moreton (+40), arrived Worcester Foregate Street +42 and was cancelled thereafter.
1W15 0750 London Paddington to Great Malvern was held at Oxford (+17) and arrived +16.
1P22 08:56 Great Malvern to London Paddington (11:24) was started from Worcester Shrub Hill, was held at Norton (+17) and arrived +15.
09:55 Great Malvern to London Paddington due 12:23 will be started from Worcester Foregate Street.
This is due to a points failure.
Last Updated:23/12/2024 09:18
This is due to a points failure.
Last Updated:23/12/2024 09:18
and later in the day:
11:52 London Paddington to Hereford due 14:44 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:23/12/2024 07:24
15:23 London Paddington to Worcester Foregate Street due 17:47 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:23/12/2024 13:15
15:18 Hereford to London Paddington due 18:29 will be cancelled.
This is due to a shortage of train crew.
Last Updated:23/12/2024 00:40
The stock for this ran empty from Shrub Hill to Reading and picked up service there.This is due to a shortage of train crew.
Last Updated:23/12/2024 07:24
15:23 London Paddington to Worcester Foregate Street due 17:47 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:23/12/2024 13:15
15:18 Hereford to London Paddington due 18:29 will be cancelled.
This is due to a shortage of train crew.
Last Updated:23/12/2024 00:40
18:02 Worcester Foregate Street to London Paddington due 20:29 will be cancelled.
This is due to a shortage of train crew.
Last Updated:23/12/2024 13:28
The stock for this ran empty to Paddington.This is due to a shortage of train crew.
Last Updated:23/12/2024 13:28
Even later:
1W03 17:34 London Paddington to Hereford (20:25) was delayed at Didcot, left Oxford +15, was held at Evesham (+28), and arrived +31.
1W34 17:57 London Paddington to Worcester Foregate Street (20:11) arrived +19.
1W43 21:53 London Paddington to Worcester Shrub Hill was cancelled throughout ("due to unknown cause" - RTT) though the stock ran empty.
1P44 19:45 Great Malvern to London Paddington (22:24) was held at Reading (+44) and arrived +53.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Chris from Nailsea at 20:22, 22nd December 2024 |
Not necessarily ... possible scenario ... someone has messed up the staff rotas and they're investigating who that someone was. But whoever it turns out to have been, the 19:13 departure from Reading will have to wait until around 19:30 so that the staff arriving at 18:59 from Great Malvern can take a required personal needs break.
Question - why does who that someone was affect the posted source of the problem?So Peter, Lord Hendy, can specify precisely who he wants to be sacked.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 17:35, 22nd December 2024 |
But later...
18:48 London Paddington to Hereford due 21:55 will be cancelled.
This is due to a broken down train earlier today.
Last Updated:22/12/2024 17:22
This is due to a broken down train earlier today.
Last Updated:22/12/2024 17:22
... and in consequence
23/12/24 05:23 Hereford to London Paddington due 08:23 will be cancelled.
This is due to a broken down train earlier today.
Last Updated:22/12/2024 17:24
This is due to a broken down train earlier today.
Last Updated:22/12/2024 17:24
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 15:56, 22nd December 2024 |
Not necessarily ... possible scenario ... someone has messed up the staff rotas and they're investigating who that someone was. But whoever it turns out to have been, the 19:13 departure from Reading will have to wait until around 19:30 so that the staff arriving at 18:59 from Great Malvern can take a required personal needs break.
Question - why does who that someone was affect the posted source of the problem?Re: North Cotswold Line delays and cancellations - 2024 Posted by grahame at 15:15, 22nd December 2024 |
Sunday December 22
Looking good until
An ability to see into the future?
Looking good until
18:48 London Paddington to Hereford due 21:55 will be delayed at Reading.
This is due to a problem currently under investigation.
Last Updated:22/12/2024 13:21
This is due to a problem currently under investigation.
Last Updated:22/12/2024 13:21
An ability to see into the future?
Not necessarily ... possible scenario ... someone has messed up the staff rotas and they're investigating who that someone was. But whoever it turns out to have been, the 19:13 departure from Reading will have to wait until around 19:30 so that the staff arriving at 18:59 from Great Malvern can take a required personal needs break.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 14:54, 22nd December 2024 |
Sunday December 22
Looking good until
18:48 London Paddington to Hereford due 21:55 will be delayed at Reading.
This is due to a problem currently under investigation.
Last Updated:22/12/2024 13:21
This is due to a problem currently under investigation.
Last Updated:22/12/2024 13:21
An ability to see into the future?
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 16:31, 21st December 2024 |
Saturday December 21
14:50 Great Malvern to London Paddington due 17:25 has been cancelled.
This is due to a fault on this train.
Last Updated:21/12/2024 15:01
19:00 Great Malvern to London Paddington due 21:24 will be cancelled.
This is due to a fault on a train in front of this one.
Further Information
GWR has ticket acceptance with West Midland's Railway on the 19.12 Great Malvern to Worcester Foregate Street.
Passengers can then board GWR 20.02 Worcester Foregate Street to London Paddington service.
Last Updated:21/12/2024 16:00
15:52 London Paddington to Great Malvern due 18:29 will be cancelled.
This is due to a shortage of train crew.
Last Updated:21/12/2024 15:38
18:52 London Paddington to Great Malvern due 21:13 will be cancelled.
This is due to a broken down train.
Last Updated:21/12/2024 15:42
This is due to a fault on this train.
Last Updated:21/12/2024 15:01
19:00 Great Malvern to London Paddington due 21:24 will be cancelled.
This is due to a fault on a train in front of this one.
Further Information
GWR has ticket acceptance with West Midland's Railway on the 19.12 Great Malvern to Worcester Foregate Street.
Passengers can then board GWR 20.02 Worcester Foregate Street to London Paddington service.
Last Updated:21/12/2024 16:00
15:52 London Paddington to Great Malvern due 18:29 will be cancelled.
This is due to a shortage of train crew.
Last Updated:21/12/2024 15:38
18:52 London Paddington to Great Malvern due 21:13 will be cancelled.
This is due to a broken down train.
Last Updated:21/12/2024 15:42
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 21:39, 20th December 2024 |
Friday December 20
Delays on account of a safety inspection of the track beween Reading and Oxford.
1W30 15:23 London Paddington to Foregate Street (17:47) : Reading +10, Didcot +24, held Evesham (+35), arrived Worcester Shrub Hill +34, didn't make Foregate St.
1W31 15:52 London Paddington to Great Malvern (18:26) : delayed Cholsey (+20), arrived +32.
2E14 17:04 Didcot Parkway to Evesham (18:23) : cancelled after Oxford
1W33 16:58 London Paddington to Great Malvern (19:25) : Oxford +24, held Wovercote (+30), arrived Worcester Shrub Hill +44 and cancelled thereafter.
1W03 17:34 London Paddington to Hereford : departed +13, cancelled after Oxford (+12) "due to an issue with the train crew (TG)" [RTT].
1W34 17:57 London Paddington to Worcester Foregate Street (20:11) : arrived +11
1P05 15:18 Hereford to London Paddington () : held Charlbury (+17), arrived +20.
1P40 18:06 Worcester Foregate St to London Paddington : started from Shrub Hill, held Norton (+20), arrived +1.
2E16 18:51 Evesham to Oxford : cancelled throughout.
1P42 19:04 Great Malvern to London Paddington : departed +21, arrived +17.
1P44 19:45 Great Malvern to London Paddington : started from Shrub Hill.
1P06 22:00 Hereford to London Paddington : cancelled throughout. Stock raan empty from Oxford to Paddington.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 17:49, 20th December 2024 |
Thursday December 19 was a good day, with no cancellations or short workings.
Friday December 20 was going well until:
15:23 London Paddington to Worcester Foregate Street due 17:47 is being delayed between Reading and Didcot Parkway and is now expected to be 17 minutes late.
This is due to a safety inspection of the track.
Last Updated:20/12/2024 16:15
This is due to a safety inspection of the track.
Last Updated:20/12/2024 16:15
15:52 London Paddington to Great Malvern due 18:26 is being delayed between Reading and Oxford and is now expected to be 28 minutes late.
This is due to a safety inspection of the track.
Last Updated:20/12/2024 17:02
17:04 Didcot Parkway to Evesham due 18:23 will be terminated at Oxford.
This is due to a safety inspection of the track.
Last Updated:20/12/2024 17:09
16:58 London Paddington to Great Malvern due 19:25 will call additionally at Combe, Finstock, Ascott-Under-Wychwood and Shipton.
This is due to the train making extra stops because a train was cancelled.
Last Updated:20/12/2024 17:15
This is due to a safety inspection of the track.
Last Updated:20/12/2024 17:02
17:04 Didcot Parkway to Evesham due 18:23 will be terminated at Oxford.
This is due to a safety inspection of the track.
Last Updated:20/12/2024 17:09
16:58 London Paddington to Great Malvern due 19:25 will call additionally at Combe, Finstock, Ascott-Under-Wychwood and Shipton.
This is due to the train making extra stops because a train was cancelled.
Last Updated:20/12/2024 17:15
No mention on JourneyCheck of the return working of the 'halts' train, 2E16 18:51 Evesham to Oxford (19:50).
1P05 1518 Hereford to London Paddington (18:29) was held at Charlbury (+17).
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 15:42, 18th December 2024 |
Wednesday December 18
Cancellations to services between Oxford and Worcester Foregate Street
Due to a fault with the signalling system between Oxford and Worcester Foregate Street trains have to run at reduced speed on some lines.
Train services running through these stations may be cancelled or delayed by up to 35 minutes. Disruption is expected until the end of the day.
Last Updated:18/12/2024 14:41
Due to a fault with the signalling system between Oxford and Worcester Foregate Street trains have to run at reduced speed on some lines.
Train services running through these stations may be cancelled or delayed by up to 35 minutes. Disruption is expected until the end of the day.
Last Updated:18/12/2024 14:41
14:53 London Paddington to Worcester Foregate Street due 17:04 will be started from Reading.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 14:28
15:23 London Paddington to Worcester Foregate Street due 17:47 will be cancelled.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 14:31
15:18 Worcester Foregate Street to London Paddington due 17:29 will be started from Worcester Shrub Hill.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 14:54
15:18 Hereford to London Paddington due 18:29 will be started from Oxford.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 13:46
18:02 Worcester Foregate Street to London Paddington due 20:29 will be cancelled.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 14:38
This is due to a fault with the signalling system.
Last Updated:18/12/2024 14:28
15:23 London Paddington to Worcester Foregate Street due 17:47 will be cancelled.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 14:31
15:18 Worcester Foregate Street to London Paddington due 17:29 will be started from Worcester Shrub Hill.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 14:54
15:18 Hereford to London Paddington due 18:29 will be started from Oxford.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 13:46
18:02 Worcester Foregate Street to London Paddington due 20:29 will be cancelled.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 14:38
RTT is also reporting:
1W02 11:52 London Paddington to Hereford arrived Oxford +26 and was cancelled thereafter.
1W25 12:51 London Paddington to Foregate St (15:00) arrived Worcester Shrub Hill +28 and was cancelled thereafter.
Later:
1W27 13:50 London Paddington to Great Malvern (16:15) arrived Worcester Shrub Hill +26 and was cancelled thereafter.
1W29 14:53 Paddington to Worcester Foregate St (17:04) was indeed started from Reading. It arrived Shrub Hill +38 and never made Foregate St.
16:32 Great Malvern to London Paddington due 19:29 will be started from Worcester Shrub Hill.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 15:37
17:26 Worcester Foregate Street to London Paddington due 19:52 will be started from Worcester Shrub Hill.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 17:10
This is due to a fault with the signalling system.
Last Updated:18/12/2024 15:37
17:26 Worcester Foregate Street to London Paddington due 19:52 will be started from Worcester Shrub Hill.
This is due to a fault with the signalling system.
Last Updated:18/12/2024 17:10
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 03:54, 18th December 2024 |
18:57 London Paddington to Great Malvern due 21:18 will be terminated at Worcester Shrub Hill.
It has been delayed between London Paddington and Reading and is now 62 minutes late.
This is due to a points failure.
Last Updated:17/12/2024 20:29
It has been delayed between London Paddington and Reading and is now 62 minutes late.
This is due to a points failure.
Last Updated:17/12/2024 20:29
Behind this, 1W05 19:53 London Paddington to Hereford was also delayed between Paddington and Reading, was held at Wolvercote (+32) and Ledbury and arrived +34.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 10:14, 17th December 2024 |
2E77 05:10 Oxford to Worcester Shrub Hill (06:15) was cancelled, though I can't imagine that many passengers were affected. The stock ran empty.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Witham Bobby at 09:26, 17th December 2024 |
Tuesday 17 December
Journeycheck giving a few hours notice. I suppose this may change later
14:53 London Paddington to Worcester Foregate Street due 17:04 will be cancelled.
This is due to a shortage of train crew.
Last Updated:17/12/2024 08:29
This is due to a shortage of train crew.
Last Updated:17/12/2024 08:29
17:26 Worcester Foregate Street to London Paddington due 19:52 will be cancelled.
This is due to a shortage of train crew.
Last Updated:17/12/2024 08:29
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 17:04, 16th December 2024 |
Monday December 16
My pessimism about the morning peak was mis-placed.
1P11 0516 Worcester Shrub Hill to London Paddington ran OK (and was 9 cars).
1P02 0523 Hereford to London Paddington ran OK (and was 9 cars, formed from Sunday's 18:45 Paddington - Hereford).
But
1P16 0643 Worcester Shrub Hill to Paddington was reported on Journey Check as cancelled, where as RTT has it as cancelled from Oxford to Paddington (but RTT says it ran early from Shrub Hill to Oxford).
Meanwhile,
15:52 London Paddington to Great Malvern due 18:26 will be started from Reading.
This is due to a shortage of train crew.
Last Updated:16/12/2024 15:42
This is due to a shortage of train crew.
Last Updated:16/12/2024 15:42
Later
17:34 London Paddington to Hereford due 20:25 will be started from Reading.
This is due to a shortage of train crew.
Last Updated:16/12/2024 17:27
This is due to a shortage of train crew.
Last Updated:16/12/2024 17:27
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 05:35, 15th December 2024 |
Sunday December 15
Oh dear...
08:58 Great Malvern to London Paddington due 11:27 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 00:19
13:11 Worcester Foregate Street to London Paddington due 15:30 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 00:29
13:58 Great Malvern to London Paddington due 16:27 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 01:21
This is due to a shortage of train crew.
Last Updated:15/12/2024 00:19
13:11 Worcester Foregate Street to London Paddington due 15:30 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 00:29
13:58 Great Malvern to London Paddington due 16:27 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 01:21
But later:
13:58 Great Malvern to London Paddington due 16:27 will be reinstated.
It will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:15/12/2024 06:38
It will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:15/12/2024 06:38
13:58 Great Malvern to London Paddington due 16:27 will be started from Worcester Shrub Hill.
It is being delayed at Worcester Shrub Hill and is now expected to be 45 minutes late.
This is due to a fault on this train.
Last Updated:15/12/2024 14:54
It is being delayed at Worcester Shrub Hill and is now expected to be 45 minutes late.
This is due to a fault on this train.
Last Updated:15/12/2024 14:54
15:31 Hereford to London Paddington due 18:30 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:15/12/2024 01:24
11:24 - This has disappeared from JourneyCheck.This is due to a shortage of train crew.
Last Updated:15/12/2024 01:24
17:30 Hereford to London Paddington due 20:30 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 01:01
This is due to a shortage of train crew.
Last Updated:15/12/2024 01:01
18:58 Great Malvern to London Paddington due 21:30 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:41
Later:This is due to a shortage of train crew.
Last Updated:15/12/2024 10:41
18:58 Great Malvern to London Paddington due 21:30 will be started from Worcester Shrub Hill.
This is due to congestion.
Last Updated:15/12/2024 17:41
This is due to congestion.
Last Updated:15/12/2024 17:41
20:46 Great Malvern to London Paddington due 23:45 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:51
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:51
09:47 London Paddington to Hereford due 12:58 will be started from Oxford.
This is due to a shortage of train crew.
Last Updated:15/12/2024 01:15
10:45 London Paddington to Great Malvern due 13:16 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 00:23
11:45 London Paddington to Hereford due 15:03 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:15/12/2024 01:19
11:27 : This has disappeared from JourneyCheck.This is due to a shortage of train crew.
Last Updated:15/12/2024 01:15
10:45 London Paddington to Great Malvern due 13:16 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 00:23
11:45 London Paddington to Hereford due 15:03 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:15/12/2024 01:19
12:45 London Paddington to Hereford due 16:04 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 00:27
This is due to a shortage of train crew.
Last Updated:15/12/2024 00:27
14:45 London Paddington to Great Malvern due 17:16 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:15/12/2024 14:58
This is due to a shortage of train crew.
Last Updated:15/12/2024 14:58
1W49 15:45 London Paddington to Great Malvern (18:16) departed +23, arrived Worcester Shrub Hill +28 and was cancelled thereafter.
17:45 London Paddington to Great Malvern due 20:15 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:29
19:45 London Paddington to Great Malvern due 22:16 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:41
20:45 London Paddington to Worcester Shrub Hill due 23:01 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:51
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:29
19:45 London Paddington to Great Malvern due 22:16 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:41
20:45 London Paddington to Worcester Shrub Hill due 23:01 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:15/12/2024 10:51
21:45 London Paddington to Worcester Shrub Hill due 23:59 will be cancelled.
This is due to a shortage of train crew.
Last Updated:15/12/2024 12:55
This is due to a shortage of train crew.
Last Updated:15/12/2024 12:55
Last train from Paddington to beyond Oxford is now at 18:45 - three subsequent ones all cancelled. Which is Not Good for tomorrow's morning peak.
Any bus operator that failed to run in this way would have been brought in front of the Traffic Commissioner long ago.
The 'lost mileage' figure for the Oxford - Worcester - Hereford section is 657.3 miles out of 2013.8 (33%).
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 17:10, 14th December 2024 |
20:20 Hereford to London Paddington due 23:38 will be terminated at Reading.
This is due to a shortage of train crew.
Last Updated:14/12/2024 13:03
This is due to a shortage of train crew.
Last Updated:14/12/2024 13:03
In the end, this train was cancelled after Shrub Hill.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Richard Fairhurst at 15:11, 14th December 2024 |
It definitely went via the North Cotswolds and missed out stops after Evesham. I was planning to get it; had checked it had departed from Worcester on time; only to get a text message from a relative at 9.04 saying "have you seen the 9.27 is cancelled?". I frantically jumped onto the folding bike and made it down to the 9.09 10 seconds before the doors closed!
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 14:42, 14th December 2024 |
Saturday December 14
Missing out Charlbury is most unusual.
08:28 Worcester Foregate Street to London Paddington due 10:42 will no longer call at Honeybourne, Moreton-In-Marsh, Kingham, Charlbury, Hanborough and Oxford but will call additionally at Didcot Parkway.
This is due to a fault on this train.
Last Updated:14/12/2024 08:53
This is due to a fault on this train.
Last Updated:14/12/2024 08:53
Missing out Charlbury is most unusual.
Errr....I think this all means the train went via the Stroud Valley non-stop? Leaving Oxford out seems to indicate this to me.
Looking at it on RTT (https://www.realtimetrains.co.uk/service/gb-nr:C89556/2024-12-14/detailed#allox_id=0), there are times for the whole of the Worcester -Oxford - Didcot section.
Re: North Cotswold Line delays and cancellations - 2024 Posted by ChrisB at 11:47, 14th December 2024 |
Saturday December 14
Missing out Charlbury is most unusual.
08:28 Worcester Foregate Street to London Paddington due 10:42 will no longer call at Honeybourne, Moreton-In-Marsh, Kingham, Charlbury, Hanborough and Oxford but will call additionally at Didcot Parkway.
This is due to a fault on this train.
Last Updated:14/12/2024 08:53
This is due to a fault on this train.
Last Updated:14/12/2024 08:53
Missing out Charlbury is most unusual.
Errr....I think this all means the train went via the Stroud Valley non-stop? Leaving Oxford out seems to indicate this to me.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 10:45, 14th December 2024 |
Saturday December 14
08:28 Worcester Foregate Street to London Paddington due 10:42 will no longer call at Honeybourne, Moreton-In-Marsh, Kingham, Charlbury, Hanborough and Oxford but will call additionally at Didcot Parkway.
This is due to a fault on this train.
Last Updated:14/12/2024 08:53
This is due to a fault on this train.
Last Updated:14/12/2024 08:53
Missing out Charlbury is most unusual.
18:52 London Paddington to Great Malvern due 21:13 will be cancelled.
This is due to a shortage of train crew.
Last Updated:14/12/2024 10:26
This is due to a shortage of train crew.
Last Updated:14/12/2024 10:26
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 06:44, 13th December 2024 |
Friday December 13
Several evening cancellations, which may yet be restored:
15:52 London Paddington to Great Malvern due 18:26 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:13/12/2024 04:59
17:57 London Paddington to Worcester Foregate Street due 20:11 will be cancelled.
This is due to a shortage of train crew.
Last Updated:13/12/2024 05:00
22:51 London Paddington to Worcestershire Parkway Hl due 01:06 will be cancelled.
This is due to a shortage of train crew.
Last Updated:13/12/2024 05:03
19:05 Great Malvern to London Paddington due 21:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:13/12/2024 05:02
20:56 Worcester Foregate Street to London Paddington due 23:29 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:13/12/2024 05:03
This is due to a shortage of train crew.
Last Updated:13/12/2024 04:59
17:57 London Paddington to Worcester Foregate Street due 20:11 will be cancelled.
This is due to a shortage of train crew.
Last Updated:13/12/2024 05:00
22:51 London Paddington to Worcestershire Parkway Hl due 01:06 will be cancelled.
This is due to a shortage of train crew.
Last Updated:13/12/2024 05:03
19:05 Great Malvern to London Paddington due 21:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:13/12/2024 05:02
20:56 Worcester Foregate Street to London Paddington due 23:29 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:13/12/2024 05:03
In the end, some were restored:
1W31 1552 London Paddington to Great Malvern ran OK
1W34 1757 London Paddington to Worcester Foregate Street was indeed cancelled, though the stock ran empty from Paddington to Shrub Hill.
1W45 2251 London Paddington to Worcestershire Parkway ran, though it was held at Oxford and arrived +25.
1P42 1905 Great Malvern to London Paddington ran OK
1P46 20:56 Worcester Foregate Street to London Paddington due 23:29 was indeed started from Shrub Hill
1W21 1053 London Paddington to Worcester Shrub Hill departed +16, was held at Wolvercote (+34) and arrived +35.
1P30 1316 Worcester Shrub Hill to London Paddington departed +28 and arrived +19.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 12:03, 12th December 2024 |
And after a very good Wednesday December 11...
Thursday December 12
13:18 Hereford to London Paddington due 16:25 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:12/12/2024 10:05
This is due to a shortage of train crew.
Last Updated:12/12/2024 10:05
Later : the stock of this service ran empty from Shrub Hill to Oxford and picked up service again there.
15:23 London Paddington to Worcester Foregate Street due 17:47 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:12/12/2024 08:19
18:02 Worcester Foregate Street to London Paddington due 20:27 will be cancelled.
This is due to a shortage of train crew.
Last Updated:12/12/2024 08:19
17:04 Didcot Parkway to Moreton-In-Marsh due 18:10 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:12/12/2024 04:02
18:51 Evesham to Oxford due 19:50 will be cancelled.
This is due to a shortage of train crew.
Last Updated:12/12/2024 04:02
This is due to a shortage of train crew.
Last Updated:12/12/2024 08:19
18:02 Worcester Foregate Street to London Paddington due 20:27 will be cancelled.
This is due to a shortage of train crew.
Last Updated:12/12/2024 08:19
17:04 Didcot Parkway to Moreton-In-Marsh due 18:10 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:12/12/2024 04:02
18:51 Evesham to Oxford due 19:50 will be cancelled.
This is due to a shortage of train crew.
Last Updated:12/12/2024 04:02
And later...
11:52 London Paddington to Hereford due 14:44 was terminated at Great Malvern.
This is due to a safety inspection of the track.
Last Updated:12/12/2024 14:20
15:18 Hereford to London Paddington due 18:29 will be started from Great Malvern.
This is due to a safety inspection of the track.
Last Updated:12/12/2024 14:20
This is due to a safety inspection of the track.
Last Updated:12/12/2024 14:20
15:18 Hereford to London Paddington due 18:29 will be started from Great Malvern.
This is due to a safety inspection of the track.
Last Updated:12/12/2024 14:20
Later stiil
1P46 2056 Worcester Foregate Street to Paddington was cancelled after Reading ("due to an issue with the train crew (TH)").
Re: North Cotswold Line delays and cancellations - 2024 Posted by Witham Bobby at 12:00, 12th December 2024 |
18:02 Worcester Foregate Street to London Paddington due 20:27 will be cancelled.
This is due to a shortage of train crew.
Last Updated:12/12/2024 08:19
This is due to a shortage of train crew.
Last Updated:12/12/2024 08:19
18:51 Evesham to Oxford due 19:50 will be cancelled.
This is due to a shortage of train crew.
Last Updated:12/12/2024 04:02
This is due to a shortage of train crew.
Last Updated:12/12/2024 04:02
Maybe there's time for one or both of these to be reinstated, yet?
Seems odd (to me) that the 1851 Evesham is cancelled, but there's no mention of a cancellation of the 1704 Didcot stopper that runs ECS on to Evesham as the 1812 Moreton in Marsh
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 17:33, 10th December 2024 |
Tuesday December 10
... was going well until
17:57 London Paddington to Worcester Foregate Street due 20:11 will be cancelled.
This is due to a shortage of train crew.
Last Updated:10/12/2024 11:49
This is due to a shortage of train crew.
Last Updated:10/12/2024 11:49
and (curiously)
20:56 Worcester Foregate Street to London Paddington due 23:29 will be started from Worcester Shrub Hill.
It will no longer call at Worcester Foregate Street.
This is due to a shortage of train crew.
Last Updated:10/12/2024 11:49
It will no longer call at Worcester Foregate Street.
This is due to a shortage of train crew.
Last Updated:10/12/2024 11:49
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 06:22, 10th December 2024 |
Monday December 9 - final score
Up trains
1P02 05:23 Hereford to London Paddington (08:24) : cancelled throuout, ran empty as train 5P02.
1P18 07:13 Great Malvern to London Paddington (09:42) : cancelled throughout
1P24 09:55 Great Malvern to London Paddington (12:23) : held Didcot (+31), arrived +38.
1P34 15:17 Worcester Foregate Street to London Paddington (17:29) : cancelled throughout (train crew)
1P39 17:30 Worcester Foregate St to London Paddington (19:52) : held Shrub Hill (+29) and Charlbury (+44), arrived +37.
1P40 18:02 Worcester Foregate Street to London Paddington (20:29) : started +11, held Charlbury (+26), arrived +21.
2E16 18:51 Evesham to Oxford (19:50) : held Charlbury (+23), arrived +18.
1P42 19:05 Great Malvern to London Paddington (21:26) : cancelled throughout.
Down trains
1W30 15:23 London Paddington to Worcester Foregate Street (17:47) : arrived +19
1W31 15:52 London Paddington to Great Malvern (18:26) : cancelled after Shrub Hill (crew)
1W03 17:34 London Paddington to Hereford (20:25) : started +37, +58 at Shrub Hill, arrived +79.
1W36 18:57 London Paddington to Great Malvern (21:20) : cancelled throughout (crew)
1W45 22:51 London Paddington to Worcestershire Parkway (01:06) : cancelled throughout (crew)
Re: North Cotswold Line delays and cancellations - 2024 Posted by Mark A at 20:19, 9th December 2024 |
The Great Storm of 1987 saw higher wind speeds than were brought by Darragh.
Agreed, a different animal, and terrible in different ways. I was asleep but am led to believe that in many places the high winds were experienced for only a quarter of an hour and then it passed. A feature was that, again in certain locations, the winds above the ground but at no great height were very much stronger than those experienced at ground level - and concentrated in gusts, and the real mayhem was caused when a gust happened to briefly descend to ground level - think 'Catspaw' but even more murderous - we certainly saw that locally as, whereas a lot of structures and trees were generally roughed up and there was felled stuff all over the shop, something on a different scale had simply taken the tops off most of the trees across a swathe of a small wood in the local park and there, it looked as if a giant lawnmower had been at work.
The other odd thing was the previous evening: we walked home around 10:30 pm, the air very still, remarkably warm for October and frogs for some reason vocal to the extent that anyone passing froggy environments had cause to wonder 'What on earth is making that racket?'
For all I know they were saying to humans: 'You don't know this yet but tomorrow morning you'll all be staring puzzled at the kettle while the people in charge of the National Grid are busy organising a black start of the south east of the UK's grid'.
Not sure what would have been involved in restoring power to the south east's railways that day, or the underground for that matter.
Mark
Re: North Cotswold Line delays and cancellations - 2024 Posted by IndustryInsider at 19:45, 9th December 2024 |
I'll just stick to reporting on the bits I notice of the shockingly poor performance of GWR on the OWW in future
17:34 London Paddington to Hereford due 20:25 will be cancelled.
This is due to a shortage of train crew.
Last Updated:09/12/2024 15:50
This is due to a shortage of train crew.
Last Updated:09/12/2024 15:50
That ended up being reinstated. You’re not having a good day! .
It did run quite late though, and a subsequent train has been cancelled.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Witham Bobby at 16:01, 9th December 2024 |
I'll just stick to reporting on the bits I notice of the shockingly poor performance of GWR on the OWW in future
17:34 London Paddington to Hereford due 20:25 will be cancelled.
This is due to a shortage of train crew.
Last Updated:09/12/2024 15:50
This is due to a shortage of train crew.
Last Updated:09/12/2024 15:50
Re: North Cotswold Line delays and cancellations - 2024 Posted by Witham Bobby at 15:58, 9th December 2024 |
That's me put in my place then
Re: North Cotswold Line delays and cancellations - 2024 Posted by ChrisB at 10:50, 9th December 2024 |
Your memory is faulty....just some that are listed on Wikipedia -
The roofs and canopies at Limehouse and Benfleet stations were destroyed, and £300,000 of damage was caused to construction work on a new train ferry pier at Dover Western Docks station.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Witham Bobby at 10:42, 9th December 2024 |
Reasonable, in this weather instance. And only three in the West.
Given the exceptional weather - yes entirely reasonable.
Of course it may beg the question as to how much more as a country we need to do by way of climate change adaptation works to make structures more wind resilient in future. You may ask at what cost but one opposition politician suggested that that might be cheaper than carbon net zero, but then I get the impression they meant leave it for the next generation to pick up the bill rather than thinking it needed doing now.
Without wishing to sound like a character in "The Vicar of Dibley", The Great Storm of 1987 saw higher wind speeds than were brought by Darragh. There was significant damage to trees, power lines and buildings. But I don't remember station canopies being blown off.
There is nothing new about the sort of weather we experienced last weekend, other than that storms get given names and our institutions seem less capable of coping than they used to be
Re: North Cotswold Line delays and cancellations - 2024 Posted by Witham Bobby at 10:38, 9th December 2024 |
19:05 Great Malvern to London Paddington due 21:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:09/12/2024 09:46
This is due to a shortage of train crew.
Last Updated:09/12/2024 09:46
22:51 London Paddington to Worcestershire Parkway Hl due 01:06 will be cancelled.
This is due to a shortage of train crew.
Last Updated:09/12/2024 04:16
This is due to a shortage of train crew.
Last Updated:09/12/2024 04:16
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 18:39, 8th December 2024 |
A shame that services couldn't run to Worcestershire Parkway and reverse there. I see an ECS made it through Shrub Hill earlier: https://www.realtimetrains.co.uk/service/gb-nr:36768/2024-12-08/detailed
Control has been listening:
18:48 London Paddington to Hereford due 21:55 will be reinstated.
It will be terminated at Worcestershire Parkway Hl.
This is due to severe weather.
Last Updated:08/12/2024 17:16
It will be terminated at Worcestershire Parkway Hl.
This is due to severe weather.
Last Updated:08/12/2024 17:16
Later (21:20), this train, 1W08 18:48 London Paddington to Hereford, made it to Worcester Shrub Hill OK, but was cancelled thereafter.
And later trains from London are explicitly listed as cancelled on JourneyCheck:
19:48 London Paddington to Great Malvern due 22:16 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 17:16
20:48 London Paddington to Worcester Shrub Hill due 23:00 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 17:16
21:48 London Paddington to Worcester Shrub Hill due 23:59 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 17:16
19:58 Great Malvern to London Paddington due 22:35 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 15:30
20:46 Great Malvern to London Paddington due 23:40 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 15:30
This is due to severe weather.
Last Updated:08/12/2024 17:16
20:48 London Paddington to Worcester Shrub Hill due 23:00 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 17:16
21:48 London Paddington to Worcester Shrub Hill due 23:59 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 17:16
19:58 Great Malvern to London Paddington due 22:35 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 15:30
20:46 Great Malvern to London Paddington due 23:40 will be cancelled.
This is due to severe weather.
Last Updated:08/12/2024 15:30
Having got the 18:48 to Shrub Hill, there is at least one 9-car unit there for Monday morning. Some of the morning peak is already cancelled:
09/12/24 05:23 Hereford to London Paddington due 08:24 will be cancelled.
This is due to more trains than usual needing repairs at the same time.
Last Updated:08/12/2024 20:10
09/12/24 07:25 Worcester Shrub Hill to London Paddington due 10:00 will be cancelled.
This is due to more trains than usual needing repairs at the same time.
Last Updated:08/12/2024 20:10
This is due to more trains than usual needing repairs at the same time.
Last Updated:08/12/2024 20:10
09/12/24 07:25 Worcester Shrub Hill to London Paddington due 10:00 will be cancelled.
This is due to more trains than usual needing repairs at the same time.
Last Updated:08/12/2024 20:10
The 07:25 is the one that goes via Stroud.
Meanwhile, the 21:48 from Paddington did operate after all, so there's now two 9-car units for Monday.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 18:35, 8th December 2024 |
Cancellations to services between Oxford and Worcester Foregate Street
Following severe weather between Oxford and Worcester Foregate Street all lines have now reopened.
Train services running through these stations will be cancelled or delayed. Disruption is expected until the end of the day.
Customer Advice
Disruption on Saturday 7 December 2024 and Sunday 8 December 2024
Following red and amber weather warnings in relation to Storm Darragh on parts of our network, we are advising customers to change their plans if possible this weekend. Strong winds mean speed restrictions will be in place across the network, increasing journey times. Fallen trees and other debris may also impact services causing severe delays and cancellations.
-
Ticket Easement;
Customers with tickets for travel on GWR services on Saturday 7 and Sunday 8 December can be used on Monday 9 December. If you no longer wish to travel this weekend you can claim a full refund at GWR.com/help-and-support/refunds.
-
Passengers can use their GWR tickets on the following bus services:-
Stagecoach 33 - Gloucester Bus Station - Hereford
Stagecoach 71 - Gloucester Bus Station - Ashchurch for Tewkesbury Station
Replacement road transport will be very limited with no confirmed times due to weather and road conditions
Passengers are advised Not to travel.
We're sorry for the delay to your journey.
We will update this message with more information when we have it.
Further Information
An update will follow within the next 2 hours.
If you require further information please speak to our staff at the station or on the train, use the Customer Help Point, tweet us @GWRHelp or call National Rail Enquiries on 03457 484 950.
If you arrive at your destination 15 or more minutes late because your GWR train was delayed or cancelled, you can claim Delay Repay compensation. Please keep your ticket and visit GWR.com/DelayRepay
Last Updated:08/12/2024 18:24
Following severe weather between Oxford and Worcester Foregate Street all lines have now reopened.
Train services running through these stations will be cancelled or delayed. Disruption is expected until the end of the day.
Customer Advice
Disruption on Saturday 7 December 2024 and Sunday 8 December 2024
Following red and amber weather warnings in relation to Storm Darragh on parts of our network, we are advising customers to change their plans if possible this weekend. Strong winds mean speed restrictions will be in place across the network, increasing journey times. Fallen trees and other debris may also impact services causing severe delays and cancellations.
-
Ticket Easement;
Customers with tickets for travel on GWR services on Saturday 7 and Sunday 8 December can be used on Monday 9 December. If you no longer wish to travel this weekend you can claim a full refund at GWR.com/help-and-support/refunds.
-
Passengers can use their GWR tickets on the following bus services:-
Stagecoach 33 - Gloucester Bus Station - Hereford
Stagecoach 71 - Gloucester Bus Station - Ashchurch for Tewkesbury Station
Replacement road transport will be very limited with no confirmed times due to weather and road conditions
Passengers are advised Not to travel.
We're sorry for the delay to your journey.
We will update this message with more information when we have it.
Further Information
An update will follow within the next 2 hours.
If you require further information please speak to our staff at the station or on the train, use the Customer Help Point, tweet us @GWRHelp or call National Rail Enquiries on 03457 484 950.
If you arrive at your destination 15 or more minutes late because your GWR train was delayed or cancelled, you can claim Delay Repay compensation. Please keep your ticket and visit GWR.com/DelayRepay
Last Updated:08/12/2024 18:24
Re: North Cotswold Line delays and cancellations - 2024 Posted by ChrisB at 17:15, 8th December 2024 |
I suspect it's crew facilities?....otherwise they surely could run at least to Evesham where turn-back ability is present?
Re: North Cotswold Line delays and cancellations - 2024 Posted by Richard Fairhurst at 17:10, 8th December 2024 |
A shame that services couldn't run to Worcestershire Parkway and reverse there. I see an ECS made it through Shrub Hill earlier: https://www.realtimetrains.co.uk/service/gb-nr:36768/2024-12-08/detailed
Re: North Cotswold Line delays and cancellations - 2024 Posted by ellendune at 16:10, 8th December 2024 |
Reasonable, in this weather instance. And only three in the West.
Given the exceptional weather - yes entirely reasonable.
Of course it may beg the question as to how much more as a country we need to do by way of climate change adaptation works to make structures more wind resilient in future. You may ask at what cost but one opposition politician suggested that that might be cheaper than carbon net zero, but then I get the impression they meant leave it for the next generation to pick up the bill rather than thinking it needed doing now.
Re: North Cotswold Line delays and cancellations - 2024 Posted by ChrisB at 15:23, 8th December 2024 |
Reasonable, in this weather instance. And only three in the West.
Re: North Cotswold Line delays and cancellations - 2024 Posted by grahame at 15:21, 8th December 2024 |
More canopy problems. Shrub Hill this time. Control completely overwhelmed as usual so contingency arrangements virtually non-existent.
Why is it all the station canopies - have they not been specified / maintained to a standard that's needed to withstand the weather? Do Network Rail have some questions to answer, or is this level of failure reasonable?
Re: North Cotswold Line delays and cancellations - 2024 Posted by IndustryInsider at 15:10, 8th December 2024 |
Nothing running at all this afternoon or evening.
More canopy problems. Shrub Hill this time. Control completely overwhelmed as usual so contingency arrangements virtually non-existent.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Richard Fairhurst at 14:35, 8th December 2024 |
Nothing running at all this afternoon or evening.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 08:51, 8th December 2024 |
Saturday:
1W25 1253 London Paddington to Worcester Foregate St (15:11) departed +30, arrived Shrub Hill +37 and failed to get to Foregate St.
This one sits at Shrub Hill until it forms 1P39 2003 Worcester Foregate Street to London Paddington, which did indeed start from Foregate St.
Sunday December 8
One cancellation and two curious short workings.
10:48 London Paddington to Great Malvern due 13:15 will be cancelled.
This is due to a shortage of train crew.
Last Updated:08/12/2024 02:39
13:58 Great Malvern to London Paddington due 16:35 will be started from Reading.
This is due to a shortage of train crew.
Last Updated:08/12/2024 02:48
13:48 London Paddington to Great Malvern due 16:17 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:08/12/2024 02:39
This is due to a shortage of train crew.
Last Updated:08/12/2024 02:39
13:58 Great Malvern to London Paddington due 16:35 will be started from Reading.
This is due to a shortage of train crew.
Last Updated:08/12/2024 02:48
13:48 London Paddington to Great Malvern due 16:17 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:08/12/2024 02:39
20:46 Great Malvern to London Paddington due 23:40 will be terminated at Reading.
This is due to a shortage of train crew.
Last Updated:08/12/2024 09:10
This is due to a shortage of train crew.
Last Updated:08/12/2024 09:10
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 12:47, 7th December 2024 |
I spoke too soon:
09:50 London Paddington to Hereford due 12:43 will be terminated at Great Malvern.
This is due to severe weather.
Last Updated:07/12/2024 11:51
Though RTT has it running beyond Malvern.This is due to severe weather.
Last Updated:07/12/2024 11:51
10:52 London Paddington to Great Malvern due 13:25 will be cancelled.
This is due to severe weather.
Last Updated:07/12/2024 10:45
11:50 London Paddington to Hereford due 14:43 has been cancelled.
This is due to a broken down train.
Last Updated:07/12/2024 12:07
13:20 Hereford to London Paddington due 16:22 will be started from Great Malvern.
This is due to severe weather.
Last Updated:07/12/2024 11:51
14:50 Great Malvern to London Paddington due 17:25 will be cancelled.
This is due to severe weather.
Last Updated:07/12/2024 10:45
15:13 Hereford to London Paddington due 18:24 will be cancelled.
This is due to a broken down train.
Last Updated:07/12/2024 12:07
This is due to severe weather.
Last Updated:07/12/2024 10:45
11:50 London Paddington to Hereford due 14:43 has been cancelled.
This is due to a broken down train.
Last Updated:07/12/2024 12:07
13:20 Hereford to London Paddington due 16:22 will be started from Great Malvern.
This is due to severe weather.
Last Updated:07/12/2024 11:51
14:50 Great Malvern to London Paddington due 17:25 will be cancelled.
This is due to severe weather.
Last Updated:07/12/2024 10:45
15:13 Hereford to London Paddington due 18:24 will be cancelled.
This is due to a broken down train.
Last Updated:07/12/2024 12:07
Both the 09:50 Paddington - Hereford and 13:20 return operated all the way to Hereford and back.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 07:11, 7th December 2024 |
Saturday December 7:
Our line has got off lightly from Storm Darragh:
06:18 Hereford to London Paddington due 09:23 will be cancelled.
This is due to a tree blocking the railway.
Last Updated:07/12/2024 05:51
This is due to a tree blocking the railway.
Last Updated:07/12/2024 05:51
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 05:12, 6th December 2024 |
Fortunately, the closure for flooding didn't last long - later trains ran to Malvern and Hereford again.
Friday December 6
Advance warning of cancellations (these may get reinstated during the day):
19:05 Great Malvern to London Paddington due 21:26 will be cancelled.
This is due to a shortage of train crew.
Last Updated:06/12/2024 01:33
15:52 London Paddington to Great Malvern due 18:26 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:06/12/2024 01:33
22:51 London Paddington to Worcestershire Parkway Hl due 01:06 will be cancelled.
This is due to a shortage of train crew.
Last Updated:06/12/2024 01:33
This is due to a shortage of train crew.
Last Updated:06/12/2024 01:33
15:52 London Paddington to Great Malvern due 18:26 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:06/12/2024 01:33
22:51 London Paddington to Worcestershire Parkway Hl due 01:06 will be cancelled.
This is due to a shortage of train crew.
Last Updated:06/12/2024 01:33
But by 14:15 we'd found a crew for the first two, leaving
22:51 London Paddington to Worcestershire Parkway Hl due 01:06 will be cancelled.
This is due to a shortage of train crew.
Last Updated:06/12/2024 01:33
This is due to a shortage of train crew.
Last Updated:06/12/2024 01:33
In the end, the stock of the 22:51 ran empty to Shrub Hill.
Re: North Cotswold Line delays and cancellations - 2024 Posted by ChrisB at 20:46, 5th December 2024 |
From Journeycheck
Following heavy rain flooding the railway between Worcester Foregate Street and Hereford all lines have now reopened.
Impact:
Train services running through these stations may be cancelled, delayed or revised. Disruption is expected until the end of the day.
Customer Advice:
We are sorry for the delay to your journey today.
Can you tell me more about the incident?
We have received reports of flooding between Great Malvern and Malvern Link. Network Rail engineers will be heading to site to asses the severity.
When flood water rises above the rails, we cannot run our services to prevent damage to the train and track. Flooding can also cause a short circuit and cut the power to signalling and important trackside equipment.
More information will follow as we have it.
What are my alternatives?
We appreciate that this will have disrupted your travel plans, especially those on Advance purchase tickets, please note that you will be able to use your ticket on a later train today.
To assist you with your journey:
Rail replacement will be operating between Worcester Shrub Hill and Hereford, calling at all stations, from 19:00 at Worcester Shrub Hill and from 19:45 at Hereford.
If you require any further assistance or information please speak to a member of Train Crew or Station Staff. Alternatively please use station help points where provided.
Check before you travel
You can check your journey using the National Rail Enquires real time Journey Planner
Impact:
Train services running through these stations may be cancelled, delayed or revised. Disruption is expected until the end of the day.
Customer Advice:
We are sorry for the delay to your journey today.
Can you tell me more about the incident?
We have received reports of flooding between Great Malvern and Malvern Link. Network Rail engineers will be heading to site to asses the severity.
When flood water rises above the rails, we cannot run our services to prevent damage to the train and track. Flooding can also cause a short circuit and cut the power to signalling and important trackside equipment.
More information will follow as we have it.
What are my alternatives?
We appreciate that this will have disrupted your travel plans, especially those on Advance purchase tickets, please note that you will be able to use your ticket on a later train today.
To assist you with your journey:
Rail replacement will be operating between Worcester Shrub Hill and Hereford, calling at all stations, from 19:00 at Worcester Shrub Hill and from 19:45 at Hereford.
If you require any further assistance or information please speak to a member of Train Crew or Station Staff. Alternatively please use station help points where provided.
Check before you travel
You can check your journey using the National Rail Enquires real time Journey Planner
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 18:50, 5th December 2024 |
Later there are bigger problems:
Due to heavy rain flooding the railway between Worcester Foregate Street and Hereford all lines are closed.
Train services running through these stations may be cancelled, delayed or revised. Disruption is expected until the end of the day.
[...]
Can you tell me more about the incident?
We have received reports of flooding between Great Malvern and Malvern Link. Network Rail engineers will be heading to site to asses the severity.
[...]
Rail replacement will be operating between Worcester Shrub Hill and Hereford, calling at all stations, from 19:00 at Worcester Shrub Hill and from 19:45 at Hereford.
Last Updated:05/12/2024 18:16
Train services running through these stations may be cancelled, delayed or revised. Disruption is expected until the end of the day.
[...]
Can you tell me more about the incident?
We have received reports of flooding between Great Malvern and Malvern Link. Network Rail engineers will be heading to site to asses the severity.
[...]
Rail replacement will be operating between Worcester Shrub Hill and Hereford, calling at all stations, from 19:00 at Worcester Shrub Hill and from 19:45 at Hereford.
Last Updated:05/12/2024 18:16
1W31 1552 London Paddington to Great Malvern was cancelled after Worcester Shrub Hill. [RTT]
19:05 Great Malvern to London Paddington due 21:26 will be started from Worcester Shrub Hill.
This is due to heavy rain flooding the railway.
Last Updated:05/12/2024 17:52
This is due to heavy rain flooding the railway.
Last Updated:05/12/2024 17:52
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 15:05, 5th December 2024 |
As widely predicted, no Up Parly this morning
2E80 0700 Worcester Shrub Hill to Didcot Parkway
RTT
2E80 0700 Worcester Shrub Hill to Didcot Parkway
This service was cancelled due to the train operator's request (TB).
RTT
... and this afternoon:
17:04 Didcot Parkway to Moreton-In-Marsh due 18:10 will be cancelled.
This is due to more trains than usual needing repairs at the same time.
Last Updated:05/12/2024 13:54
18:51 Evesham to Oxford due 19:50 will be cancelled.
This is due to more trains than usual needing repairs at the same time.
Last Updated:05/12/2024 13:54
This is due to more trains than usual needing repairs at the same time.
Last Updated:05/12/2024 13:54
18:51 Evesham to Oxford due 19:50 will be cancelled.
This is due to more trains than usual needing repairs at the same time.
Last Updated:05/12/2024 13:54
Later:
16:32 Great Malvern to London Paddington due 19:29 will no longer call at Worcestershire Parkway Hl and Pershore.
It has been delayed at Great Malvern and is now 18 minutes late.
This is due to a lorry colliding with a bridge earlier on this train's journey.
Last Updated:05/12/2024 17:03
Cutting out the stops means it's only +7 at Evesham.It has been delayed at Great Malvern and is now 18 minutes late.
This is due to a lorry colliding with a bridge earlier on this train's journey.
Last Updated:05/12/2024 17:03
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 13:40, 5th December 2024 |
09:52 London Paddington to Hereford due 12:46 will be terminated at Great Malvern.
It has been delayed between London Paddington and Reading and is now 20 minutes late.
This is due to trespassers on the railway earlier today.
Last Updated:05/12/2024 12:28
13:18 Hereford to London Paddington due 16:24 will be started from Great Malvern.
This is due to trespassers on the railway earlier today.
Last Updated:05/12/2024 12:28
It has been delayed between London Paddington and Reading and is now 20 minutes late.
This is due to trespassers on the railway earlier today.
Last Updated:05/12/2024 12:28
13:18 Hereford to London Paddington due 16:24 will be started from Great Malvern.
This is due to trespassers on the railway earlier today.
Last Updated:05/12/2024 12:28
The 09:52 arrived Great Malvern +28.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Witham Bobby at 11:07, 5th December 2024 |
As widely predicted, no Up Parly this morning
2E80 0700 Worcester Shrub Hill to Didcot Parkway
This service was cancelled due to the train operator's request (TB).
RTT
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 05:07, 5th December 2024 |
Wednesday December 4
In the evening
1W05 1953 London Paddington to Hereford (22:58) was a 9-car set instead of JourneyCheck's warning about 5 cars. Forms 05:23 Hereford - Paddington.
1W41 2052 London Paddington to Great Malvern was cancelled throughout. Should form 07:25 Shrub Hill - Cheltenham - Paddington.
1W43 2153 London Paddington to Shrub Hill (00:01), a 9 car set, was cancelled after Oxford due to train crew. Should form 06:43 Shrub Hill - Paddington.
1W45 2251 London Paddington to Worcestershire Parkway (01:06) was a nine-car set. Should form 05:14 Shrub Hill - Paddington.
Thursday December 5
The evening's moves should have meant problems during this morning's peaks, but once again Control is being creative.
JourneyCheck has the 'halts' train being cancelled:
07:00 Worcester Shrub Hill to Didcot Parkway due 08:46 will be cancelled.
This is due to a fault on this train.
Last Updated:05/12/2024 03:50
But the positioning journey for this, 2E77 0510 Oxford to Worcester Shrub Hill (06:15), is today being operated by a 9-car IET. Yes, it's yesterday's Oxford cancellation, finishing yesterday's journey.This is due to a fault on this train.
Last Updated:05/12/2024 03:50
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 22:21, 4th December 2024 |
17:57 London Paddington to Worcester Foregate Street due 20:11 will no longer call at Hanborough, Charlbury, Shipton and Kingham.
It is being delayed at London Paddington.
This is due to a road vehicle colliding with a bridge.
Last Updated:04/12/2024 18:19
It is being delayed at London Paddington.
This is due to a road vehicle colliding with a bridge.
Last Updated:04/12/2024 18:19
1W34 17:57 London Paddington to Worcester Foregate Street (20:11) departed +27 and, after skipping stops from Oxford to Moreton (+26), was held at Evesham (+33) and arrived Foregate St +38.
The next one, 1W36 1857 London Paddington to Great Malvern, departed +11, was delayed to Reading (+24), arrived Shrub Hill +31 and Worcester Foregate Street +42, and was cancelled thereafter.
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 18:43, 4th December 2024 |
17:57 London Paddington to Worcester Foregate Street due 20:11 will no longer call at Hanborough, Charlbury, Shipton and Kingham.
It is being delayed at London Paddington.
This is due to a road vehicle colliding with a bridge.
Last Updated:04/12/2024 18:19
It is being delayed at London Paddington.
This is due to a road vehicle colliding with a bridge.
Last Updated:04/12/2024 18:19
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 13:19, 4th December 2024 |
But some good news:
13:50 London Paddington to Great Malvern due 16:15 will now run as scheduled.
Last Updated:04/12/2024 13:13
16:32 Great Malvern to London Paddington due 19:29 will now run as scheduled.
Last Updated:04/12/2024 13:13
Last Updated:04/12/2024 13:13
16:32 Great Malvern to London Paddington due 19:29 will now run as scheduled.
Last Updated:04/12/2024 13:13
But a bit later there was a bridge strike near Moreton.
1W25 12:51 London Paddington to Foregate St was held at Moreton (+22), arrived Worcester Shrub Hill +29 and never made it to Foregate St.
1P04 13:18 Hereford to London Paddington left Honeybourne +19 and arrived Paddington +20.
1P34 15:17 Foregate St to London Paddington was started from Worcester Shrub Hill (+12), was held at Charlbury (+29) ...
And today's prize for shortest operated journey goes to
18:02 Worcester Foregate Street to London Paddington due 20:29 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:04/12/2024 17:28
This is due to a shortage of train crew.
Last Updated:04/12/2024 17:28
Re: North Cotswold Line delays and cancellations - 2024 Posted by ChrisB at 09:40, 4th December 2024 |
Bang goes the 0643 from Shrub Hill tomorrow then....
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 05:39, 4th December 2024 |
A couple of short-formations this evening which will impact upon peak up services tomorrow morning:
which seem to make up the stock for the next morning's 0523 Hereford to London Paddington and 0643 Worcester Shrub Hill to London Paddington services.
Facilities on the 19:53 London Paddington to Hereford due 22:58.
Will be formed of 5 coaches instead of 9. There are no reservations on this service
Facilities on the 21:53 London Paddington to Worcester Shrub Hill due 00:01.
Will be formed of 5 coaches instead of 9. There are no reservations on this service
Will be formed of 5 coaches instead of 9. There are no reservations on this service
Facilities on the 21:53 London Paddington to Worcester Shrub Hill due 00:01.
Will be formed of 5 coaches instead of 9. There are no reservations on this service
which seem to make up the stock for the next morning's 0523 Hereford to London Paddington and 0643 Worcester Shrub Hill to London Paddington services.
Overnight, someone has swapped the next-day workings at Shrub Hill -
the 5-car set is on 1P11 0514 Worcester Shrub Hill to London Paddington (07:24), and
a 9-car set on 1P16 0643 Worcester Shrub Hill to London Paddington (08:44).
But it still means that three of the first four London trains from Worcester to Oxford are five cars instead of nine.
And none of this is reported in the 'Formations' section of JourneyCheck.
Later in the day:
13:50 London Paddington to Great Malvern due 16:15 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:04/12/2024 02:56
16:32 Great Malvern to London Paddington due 19:29 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:04/12/2024 02:56
20:52 London Paddington to Great Malvern due 23:13 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:04/12/2024 03:03
21:53 London Paddington to Worcester Shrub Hill due 00:01 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:04/12/2024 03:11
This is due to a shortage of train crew.
Last Updated:04/12/2024 02:56
16:32 Great Malvern to London Paddington due 19:29 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:04/12/2024 02:56
20:52 London Paddington to Great Malvern due 23:13 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:04/12/2024 03:03
21:53 London Paddington to Worcester Shrub Hill due 00:01 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:04/12/2024 03:11
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 20:40, 3rd December 2024 |
A couple of short-formations this evening which will impact upon peak up services tomorrow morning:
Facilities on the 19:53 London Paddington to Hereford due 22:58.
Will be formed of 5 coaches instead of 9. There are no reservations on this service
Facilities on the 21:53 London Paddington to Worcester Shrub Hill due 00:01.
Will be formed of 5 coaches instead of 9. There are no reservations on this service
Will be formed of 5 coaches instead of 9. There are no reservations on this service
Facilities on the 21:53 London Paddington to Worcester Shrub Hill due 00:01.
Will be formed of 5 coaches instead of 9. There are no reservations on this service
which seem to make up the stock for the next morning's 0523 Hereford to London Paddington and 0643 Worcester Shrub Hill to London Paddington services.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 17:05, 3rd December 2024 |
Tuesday December 3
A good day until
1W27 13:50 London Paddington to Great Malvern : cancelled after Worcester Shrub Hill "due to a problem with train monitoring systems (PT)" [RTT].
1P38 16:32 Great Malvern to London Paddington : started from Shrub Hill.
And 1P38 is now ahead of
15:18 Hereford to London Paddington due 18:29 has been delayed at Shelwick Jn and is now 40 minutes late.
This is due to trespassers on the railway.
Last Updated:03/12/2024 16:53
This is due to trespassers on the railway.
Last Updated:03/12/2024 16:53
17:45 : But now...
15:18 Hereford to London Paddington due 18:29 will be terminated at Reading.
It has been delayed at Shelwick Jn and is now 40 minutes late.
This is due to trespassers on the railway.
Last Updated:03/12/2024 17:15
Having been held at Norton, it's now +60.It has been delayed at Shelwick Jn and is now 40 minutes late.
This is due to trespassers on the railway.
Last Updated:03/12/2024 17:15
18:57 London Paddington to Great Malvern due 21:20 will be started from Reading.
This is due to trespassers on the railway.
Will be formed of 5 coaches instead of 9.
Last Updated:03/12/2024 17:15
This is due to trespassers on the railway.
Will be formed of 5 coaches instead of 9.
Last Updated:03/12/2024 17:15
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 16:44, 2nd December 2024 |
Monday December 2
17:04 Didcot Parkway to Moreton-In-Marsh due 18:10 will be terminated at Oxford.
This is due to more trains than usual needing repairs at the same time.
Last Updated:02/12/2024 15:57
18:51 Evesham to Oxford due 19:50 will be cancelled.
This is due to more trains than usual needing repairs at the same time.
This is due to more trains than usual needing repairs at the same time.
Last Updated:02/12/2024 15:57
18:51 Evesham to Oxford due 19:50 will be cancelled.
This is due to more trains than usual needing repairs at the same time.
Halts calls being made by 1W33 16:58 London Paddington to Great Malvern.
20:52 London Paddington to Great Malvern due 23:13 will be started from Reading.
This is due to a shortage of train crew.
Last Updated:02/12/2024 02:00
21:53 London Paddington to Worcester Shrub Hill due 00:01 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:02/12/2024 02:00
This is due to a shortage of train crew.
Last Updated:02/12/2024 02:00
21:53 London Paddington to Worcester Shrub Hill due 00:01 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:02/12/2024 02:00
19:00 : The last two have now disappeared from the JourneyCheck lists.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 07:13, 1st December 2024 |
Sunday December 1
14:50 London Paddington to Great Malvern due 17:16 will be cancelled.
This is due to a shortage of train crew.
Last Updated:01/12/2024 02:00
This is due to a shortage of train crew.
Last Updated:01/12/2024 02:00
This is a 'one-way' working - there's no return journey back to Paddington. Instead, the stock goes back to Stoke Gifford empty - 17:30 from Great Malvern, arrive Stoke Gifford 19:53.
Later (13:17):
10:50 London Paddington to Great Malvern due 13:15 will be terminated at Worcester Foregate Street.
It has been delayed between London Paddington and Oxford and is now 53 minutes late.
This is due to earlier engineering works not being finished on time.
Last Updated:01/12/2024 12:58
13:58 Great Malvern to London Paddington due 16:32 will be started from Worcester Foregate Street.
This is due to earlier engineering works not being finished on time.
Last Updated:01/12/2024 12:58
It has been delayed between London Paddington and Oxford and is now 53 minutes late.
This is due to earlier engineering works not being finished on time.
Last Updated:01/12/2024 12:58
13:58 Great Malvern to London Paddington due 16:32 will be started from Worcester Foregate Street.
This is due to earlier engineering works not being finished on time.
Last Updated:01/12/2024 12:58
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 14:28, 30th November 2024 |
And in the afternoon, it's points failure at Didcot:
11:55 Great Malvern to London Paddington due 14:23 will be terminated at Reading.
It has been delayed at Didcot Parkway and is now 33 minutes late.
This is due to a points failure.
Last Updated:30/11/2024 14:19
13:05 Worcester Foregate Street to London Paddington due 15:22 will no longer call at Didcot Parkway.
This is due to a points failure.
Last Updated:30/11/2024 14:08
14:52 London Paddington to Great Malvern due 17:14 will be started from Reading.
This is due to a points failure.
Last Updated:30/11/2024 14:19
It has been delayed at Didcot Parkway and is now 33 minutes late.
This is due to a points failure.
Last Updated:30/11/2024 14:19
13:05 Worcester Foregate Street to London Paddington due 15:22 will no longer call at Didcot Parkway.
This is due to a points failure.
Last Updated:30/11/2024 14:08
14:52 London Paddington to Great Malvern due 17:14 will be started from Reading.
This is due to a points failure.
Last Updated:30/11/2024 14:19
13:20 Hereford to London Paddington due 16:22 will no longer call at Didcot Parkway.
This is due to a points failure.
Last Updated:30/11/2024 14:24
This is due to a points failure.
Last Updated:30/11/2024 14:24
14:50 Great Malvern to London Paddington due 17:25 will no longer call at Didcot Parkway.
This is due to a points failure.
Last Updated:30/11/2024 16:09
This is due to a points failure.
Last Updated:30/11/2024 16:09
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 08:00, 30th November 2024 |
Saturday November 30
07:43 Great Malvern to London Paddington due 10:24 will be cancelled.
This is due to a shortage of train crew.
Last Updated:30/11/2024 02:00
This is due to a shortage of train crew.
Last Updated:30/11/2024 02:00
08:40
07:52 London Paddington to Great Malvern due 10:16 has been cancelled.
This is due to a fault on this train.
Last Updated:30/11/2024 08:27
10:50 Great Malvern to London Paddington due 13:24 will be cancelled.
This is due to a fault on this train.
Last Updated:30/11/2024 08:27
This is due to a fault on this train.
Last Updated:30/11/2024 08:27
10:50 Great Malvern to London Paddington due 13:24 will be cancelled.
This is due to a fault on this train.
Last Updated:30/11/2024 08:27
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 22:00, 29th November 2024 |
And in the evening, the halts train and its return working were cancelled.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 14:56, 29th November 2024 |
A small piece of good news:
13:18 Hereford to London Paddington due 16:25 will be started from Great Malvern.
This is due to a fault with the signalling system.
Last Updated:29/11/2024 12:47
The outward journey, 1W01 0952 London Paddington to Hereford, was held at Moreton (+43), Evesham (+53) and Shrub Hill (+63), and was cancelled after Great Malvern.This is due to a fault with the signalling system.
Last Updated:29/11/2024 12:47
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 12:56, 29th November 2024 |
Meanwhile, unreported on Journeycheck, 1P26 1059 Great Malvern to London Paddington was held at Shrub Hill but has now departed +51. Holding at Shrub Hill is good. It means that alternatives are still possible - sending the train round by Stroud or decanting all the passengers into a coach. But it does block one of the two platforms.
And the following 1P28 11:57 Great Malvern to London Paddington was started from Worcester Shrub Hill (+24).
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 12:35, 29th November 2024 |
Alterations to services between Evesham and Worcester Shrub Hill
Following a fault with the signalling system between Evesham and Worcester Shrub Hill all lines have now reopened.
Train services running through these stations are returning to normal but some services may still be delayed by up to 45 minutes or revised. Disruption is expected until 13:30 29/11.
Following a fault with the signalling system between Evesham and Worcester Shrub Hill all lines have now reopened.
Train services running through these stations are returning to normal but some services may still be delayed by up to 45 minutes or revised. Disruption is expected until 13:30 29/11.
09:52 London Paddington to Hereford due 12:46 will be terminated at Worcester Foregate Street.
It will no longer call at Malvern Link, Great Malvern, Colwall, Ledbury and Hereford.
It has been delayed at Moreton-In-Marsh and is now 43 minutes late.
This is due to a fault with the signalling system.
10:53 London Paddington to Worcester Shrub Hill due 13:01 will be terminated at Oxford.
It will no longer call at Hanborough, Charlbury, Kingham, Moreton-In-Marsh, Honeybourne, Evesham, Pershore, Worcestershire Parkway Hl and Worcester Shrub Hill.
This is due to a fault with the signalling system.
13:16 Worcester Shrub Hill to London Paddington due 15:23 will be started from Oxford.
It will no longer call at Worcester Shrub Hill, Worcestershire Parkway Hl, Pershore, Evesham, Honeybourne, Moreton-In-Marsh, Kingham, Charlbury and Hanborough.
This is due to a fault with the signalling system.
13:18 Hereford to London Paddington due 16:25 will be started from Worcester Foregate Street.
It will no longer call at Hereford, Ledbury, Colwall, Great Malvern and Malvern Link.
This is due to a fault with the signalling system.
It will no longer call at Malvern Link, Great Malvern, Colwall, Ledbury and Hereford.
It has been delayed at Moreton-In-Marsh and is now 43 minutes late.
This is due to a fault with the signalling system.
10:53 London Paddington to Worcester Shrub Hill due 13:01 will be terminated at Oxford.
It will no longer call at Hanborough, Charlbury, Kingham, Moreton-In-Marsh, Honeybourne, Evesham, Pershore, Worcestershire Parkway Hl and Worcester Shrub Hill.
This is due to a fault with the signalling system.
13:16 Worcester Shrub Hill to London Paddington due 15:23 will be started from Oxford.
It will no longer call at Worcester Shrub Hill, Worcestershire Parkway Hl, Pershore, Evesham, Honeybourne, Moreton-In-Marsh, Kingham, Charlbury and Hanborough.
This is due to a fault with the signalling system.
13:18 Hereford to London Paddington due 16:25 will be started from Worcester Foregate Street.
It will no longer call at Hereford, Ledbury, Colwall, Great Malvern and Malvern Link.
This is due to a fault with the signalling system.
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 11:09, 29th November 2024 |
'Heavy rain flooding the railway' is perhaps understandable - Storm Bert and all that.
But such a litany of 'cancellation due to a shortage of train crew' shows that GWR are now merely providing a 'Monday to Friday' train service.
CfN.
But such a litany of 'cancellation due to a shortage of train crew' shows that GWR are now merely providing a 'Monday to Friday' train service.
CfN.
And even the provision of a Monday to Friday "service" seems to be becoming a struggle for GWR
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 06:44, 29th November 2024 |
Friday November 29
Not a good start. The 05:23 Hereford was cancelled yesterday evening. To that we have to add
07:13 Great Malvern to London Paddington due 09:42 will be cancelled.
This is due to a shortage of train crew.
Last Updated:29/11/2024 02:00
08:15 Worcester Shrub Hill to London Paddington due 10:23 will be terminated at Didcot Parkway.
This is due to a shortage of train crew.
Will be formed of 3 coaches instead of 5.
Last Updated:29/11/2024 04:20
This is due to a shortage of train crew.
Last Updated:29/11/2024 02:00
08:15 Worcester Shrub Hill to London Paddington due 10:23 will be terminated at Didcot Parkway.
This is due to a shortage of train crew.
Will be formed of 3 coaches instead of 5.
Last Updated:29/11/2024 04:20
The 08:15 change follows from
06:33 Swindon to Worcester Shrub Hill due 07:58 will be cancelled.
This is due to a shortage of train crew.
Last Updated:29/11/2024 02:00
This is due to a shortage of train crew.
Last Updated:29/11/2024 02:00
But someone in Control has done a crafty move with the stock. Looking in detail at RTT, the stock has been "stolen" from
07:04 Worcester Foregate Street to Bristol Temple Meads due 08:35 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:29/11/2024 02:09
This is due to a shortage of train crew.
Last Updated:29/11/2024 02:09
From Shrub Hill towards Oxford, this leaves
05:14 - 9 cars
06:43 - 9 cars
07:00 halts train - 2 cars
08:15 - 3 cars
09:15 - 9 cars
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 06:32, 29th November 2024 |
With the following rammed full 1W30 1523 London Paddington to Worcester Foregate Street service held at Oxford for 16 minutes. Just what's needed when temperatures are struggling to get above freezing.
The 15:23 was then held at Evesham (+40), arrived Foegate St +48 and was cancelled thereafter.The return working, 1P42 19:05 Great Malvern to London Paddington was started from Worcester Foregate Street, was held at Norton and Charlbury (+16), was delayed near Stockley Junction and arrived Paddington +48.
The following 1P44 1945 Great Malvern to London Paddington was delayed likewise and arrived +32.
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 19:49, 28th November 2024 |
Thursday November 28
19:53 London Paddington to Hereford due 22:58 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:28/11/2024 00:09
This is due to a shortage of train crew.
Last Updated:28/11/2024 00:09
Has now changed to a full cancellation:
19:53 London Paddington to Hereford due 22:58 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 18:13
This is due to a shortage of train crew.
Last Updated:28/11/2024 18:13
with the following knock on tomorrow morning:
29/11/24 05:23 Hereford to London Paddington due 08:24 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 18:17
This is due to a shortage of train crew.
Last Updated:28/11/2024 18:17
Re: North Cotswold Line delays and cancellations - 2024 Posted by IndustryInsider at 18:44, 28th November 2024 |
Mostly TM shortages today rather than drivers AIUI.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 17:35, 28th November 2024 |
Thursday November 28
12:51 London Paddington to Worcester Foregate Street due 15:00 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
15:17 Worcester Foregate Street to London Paddington due 17:29 will be reinstated.
It will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
15:17 Worcester Foregate Street to London Paddington due 17:29 will be reinstated.
It will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
The stock of the cancelled 12:51 ran empty from Paddington to Shrub Hill as train 5W25.
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 16:47, 28th November 2024 |
Thursday November 28
14:53 London Paddington to Worcester Foregate Street due 17:04 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
With the following rammed full 1W30 1523 London Paddington to Worcester Foregate Street service held at Oxford for 16 minutes. Just what's needed when temperatures are struggling to get above freezing.
Edit - the 14:53 was partially re-instated terminating at Oxford. But same impact and squeeze on those wishing to travel to the Cotswolds.
Re: North Cotswold Line delays and cancellations - 2024 Posted by charles_uk at 12:39, 28th November 2024 |
Somewhat concerning that "shortage of train crew" cancellations are becoming more frequent on scheduled day time weekday services.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 05:05, 28th November 2024 |
Thursday November 28
12:51 London Paddington to Worcester Foregate Street due 15:00 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
15:17 Worcester Foregate Street to London Paddington due 17:29 will be reinstated.
It will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
14:53 London Paddington to Worcester Foregate Street due 17:04 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
17:26 Worcester Foregate Street to London Paddington due 19:52 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
19:53 London Paddington to Hereford due 22:58 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:28/11/2024 00:09
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
15:17 Worcester Foregate Street to London Paddington due 17:29 will be reinstated.
It will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
14:53 London Paddington to Worcester Foregate Street due 17:04 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
17:26 Worcester Foregate Street to London Paddington due 19:52 will be cancelled.
This is due to a shortage of train crew.
Last Updated:28/11/2024 02:53
19:53 London Paddington to Hereford due 22:58 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:28/11/2024 00:09
1W15 07:50 Paddington to Great Malvern started from Reading (+19), arrived +22.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 05:00, 28th November 2024 |
and in the evening there was quite a bit of late running:
2E14 17:04 Didcot - Moreton : arrived +21
1W33 16:58 London Paddington to Great Malvern : held Wolvercote, delayed Kingham, arrived +31
1W03 17:34 London Paddington to Hereford : held Wolvercote, arrived +29
1W36 18:57 London Paddington to Great Malvern : held Evesham (+35), arrived Worcester Shrub Hill +45 and cancelled thereafter
1W05 19:53 London Paddington to Hereford : held Reading (+14) and Evesham (+25), stands at Great malvern for 14, so aarrived Hereford +16.
1P42 19:05 Great Malvern to London Paddington : started from Shrub Hill.
1P44 19:45 Great Malvern to London Paddington : departed +33, held Henwick (+41), Norton (+50), arrived +44.
1P46 20:56 Worcester Foregate Street to London Paddington : held Norton (+32), arrived +45.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 12:25, 27th November 2024 |
Wednesday November 27
09:52 London Paddington to Hereford due 12:46 will be terminated at Worcester Shrub Hill.
It has been delayed at London Paddington and is now 29 minutes late.
This is due to this train being late from the depot.
Last Updated:27/11/2024 12:02
13:18 Hereford to London Paddington due 16:25 will be started from Worcester Shrub Hill.
This is due to this train being late from the depot.
Last Updated:27/11/2024 12:02
It has been delayed at London Paddington and is now 29 minutes late.
This is due to this train being late from the depot.
Last Updated:27/11/2024 12:02
13:18 Hereford to London Paddington due 16:25 will be started from Worcester Shrub Hill.
This is due to this train being late from the depot.
Last Updated:27/11/2024 12:02
14:00
14:53 London Paddington to Worcester Foregate Street due 17:04 will be terminated at Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:27/11/2024 13:03
17:26 Worcester Foregate Street to London Paddington due 19:52 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:27/11/2024 13:03
This is due to a shortage of train crew.
Last Updated:27/11/2024 13:03
17:26 Worcester Foregate Street to London Paddington due 19:52 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:27/11/2024 13:03
But later...
17:26 Worcester Foregate Street to London Paddington due 19:52 will be cancelled.
This is due to a problem with line-side equipment.
Last Updated:27/11/2024 17:22
This is due to a problem with line-side equipment.
Last Updated:27/11/2024 17:22
18:00 : the "problem with line-side equipment" has not prevented this train from running empty back to Paddington.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 16:35, 26th November 2024 |
Tuesday November 26
1W13 0650 London Paddington to Great Malvern departed +28, arrived Worcester Shrub Hill +27 and was cancelled thereafter.
1P24 09:55 Great Malvern to London Paddington was started from Worcester Shrub Hill.
13:50 London Paddington to Great Malvern due 16:15 will be terminated at Worcester Shrub Hill.
It is being delayed at London Paddington.
This is due to a late running train being in front of this one.
Last Updated:26/11/2024 15:35
16:32 Great Malvern to London Paddington due 19:29 will be started from Worcester Shrub Hill.
This is due to a late running train being in front of this one.
Last Updated:26/11/2024 15:35
It is being delayed at London Paddington.
This is due to a late running train being in front of this one.
Last Updated:26/11/2024 15:35
16:32 Great Malvern to London Paddington due 19:29 will be started from Worcester Shrub Hill.
This is due to a late running train being in front of this one.
Last Updated:26/11/2024 15:35
1W29 14:53 London Paddington to Foregate Street was cancelled after Oxford.
17:26 Worcester Foregate Street to London Paddington due 19:52 will be started from Oxford.
This is due to a fault on this train.
Last Updated:26/11/2024 16:09
This is due to a fault on this train.
Last Updated:26/11/2024 16:09
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 05:06, 26th November 2024 |
But 1P11 0514 Worcester Shrub Hill to London Paddington is on its way.
But several subsequent ones were cancelled, as posted earlier. The full list:1P11 0514 Worcester Shrub Hill to London Paddington : ran OK (and as 9 cars)
1P02 0523 Hereford to London Paddington : cancelled throughout.
1P16 0643 Worcester Shrub Hill to London Paddington : ran OK (also 9 cars)
2E80 0700 Worcester Shrub Hill to Didcot Parkway halts train : cancelled throughout
1P18 0713 Great Malvern to London Paddington : cancelled throughout
1P20 0815 Worcester Shrub Hill to London Paddington : cancelled throughout
1P22 0856 Great Malvern to London Paddington : cancelled throughout
1P24 0955 Great Malvern to London Paddington : ran OK
- so nothing from Shrub Hill to Oxford between 06:43 and 10:16.
2E77 0510 Oxford to Worcester Shrub Hill : cancelled throughout
1W11 0553 London Paddington to Great Malvern : cancelled after Oxford
1W13 0650 London Paddington to Great Malvern : ran OK
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 05:37, 25th November 2024 |
But 1P11 0514 Worcester Shrub Hill to London Paddington is on its way.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 04:07, 25th November 2024 |
Monday November 25
Oxford - Hereford is no longer listed on the 'Line updates' part of Journeycheck, but...
05:23 Hereford to London Paddington due 08:24 will be cancelled.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
07:00 Worcester Shrub Hill to Didcot Parkway due 08:46 will be started from Oxford.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
08:56 Great Malvern to London Paddington due 11:24 will be started from Oxford.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
05:10 Oxford to Worcester Shrub Hill due 06:15 will be cancelled.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
05:53 London Paddington to Great Malvern due 08:38 will be terminated at Oxford.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
07:00 Worcester Shrub Hill to Didcot Parkway due 08:46 will be started from Oxford.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
08:56 Great Malvern to London Paddington due 11:24 will be started from Oxford.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
05:10 Oxford to Worcester Shrub Hill due 06:15 will be cancelled.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
05:53 London Paddington to Great Malvern due 08:38 will be terminated at Oxford.
This is due to heavy rain flooding the railway.
Last Updated:25/11/2024 03:00
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 03:58, 25th November 2024 |
From RTT, it looks like a handful of services this evening have run from Paddington to Oxford, then disappeared from the reports until they emerge in Worcester having gone another way - presumably Cheltenham?
As I write, the 21:36 Paddington-Worcester is pootling along the Stroud Valley, having reversed at Oxford. It was advertised (if that's the right term) to call at Swindon only.
RTT reports that three trains went that way - the 18:36, 19:36 and 21:36 from Paddington. They all ran very late, so the Stroud route can't have been easy. But Control has made certain that there's three trains ready for service at Worcester on Monday morning, though the Hereford starter won't be in place.Re: North Cotswold Line delays and cancellations - 2024 Posted by Trowres at 23:55, 24th November 2024 |
As I write, the 21:36 Paddington-Worcester is pootling along the Stroud Valley, having reversed at Oxford. It was advertised (if that's the right term) to call at Swindon only.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Richard Fairhurst at 23:23, 24th November 2024 |
From RTT, it looks like a handful of services this evening have run from Paddington to Oxford, then disappeared from the reports until they emerge in Worcester having gone another way - presumably Cheltenham?
Re: North Cotswold Line delays and cancellations - 2024 Posted by Chris from Nailsea at 18:49, 24th November 2024 |
'Heavy rain flooding the railway' is perhaps understandable - Storm Bert and all that.
But such a litany of 'cancellation due to a shortage of train crew' shows that GWR are now merely providing a 'Monday to Friday' train service.
CfN.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 14:52, 24th November 2024 |
Further changes:
13:11 Worcester Foregate Street to London Paddington due 15:46 has been cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 14:21
14:28 Hereford to London Paddington due 17:31 will be started from Worcester Shrub Hill.
This is due to heavy rain flooding the railway.
Last Updated:24/11/2024 11:05
17:30 Hereford to London Paddington due 20:46 will be started from Oxford.
This is due to heavy rain flooding the railway.
Last Updated:24/11/2024 14:19
12:36 London Paddington to Hereford due 16:04 will be terminated at Oxford.
It has been delayed at London Paddington and is now 67 minutes late.
This is due to heavy rain flooding the railway.
Last Updated:24/11/2024 14:19
This is due to a shortage of train crew.
Last Updated:24/11/2024 14:21
14:28 Hereford to London Paddington due 17:31 will be started from Worcester Shrub Hill.
This is due to heavy rain flooding the railway.
Last Updated:24/11/2024 11:05
17:30 Hereford to London Paddington due 20:46 will be started from Oxford.
This is due to heavy rain flooding the railway.
Last Updated:24/11/2024 14:19
12:36 London Paddington to Hereford due 16:04 will be terminated at Oxford.
It has been delayed at London Paddington and is now 67 minutes late.
This is due to heavy rain flooding the railway.
Last Updated:24/11/2024 14:19
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 09:25, 24th November 2024 |
Sunday November 24
08:15 Worcester Foregate Street to Reading due 10:01 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:44
11:58 Great Malvern to London Paddington due 14:31 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
13:11 Worcester Foregate Street to London Paddington due 15:46 will be started from Oxford.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
15:31 Hereford to London Paddington due 18:46 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:24
18:58 Great Malvern to London Paddington due 21:46 will be started from Oxford.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
19:58 Great Malvern to London Paddington due 22:32 will be terminated at Reading.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:35
20:46 Great Malvern to London Paddington due 23:40 will be terminated at Reading.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:32
09:18 Reading to Great Malvern due 11:15 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
10:13 Reading to Hereford due 12:58 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:23
11:36 London Paddington to Hereford due 15:04 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:24
12:36 London Paddington to Hereford due 16:04 will be reinstated.
It will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/11/2024 05:01
15:36 London Paddington to Great Malvern due 18:15 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
16:36 London Paddington to Great Malvern due 19:15 will be started from Reading.
This is due to a shortage of train crew.
Last Updated:24/11/2024 05:08
20:36 London Paddington to Worcester Shrub Hill due 23:00 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:32
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:44
11:58 Great Malvern to London Paddington due 14:31 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
13:11 Worcester Foregate Street to London Paddington due 15:46 will be started from Oxford.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
15:31 Hereford to London Paddington due 18:46 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:24
18:58 Great Malvern to London Paddington due 21:46 will be started from Oxford.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
19:58 Great Malvern to London Paddington due 22:32 will be terminated at Reading.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:35
20:46 Great Malvern to London Paddington due 23:40 will be terminated at Reading.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:32
09:18 Reading to Great Malvern due 11:15 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
10:13 Reading to Hereford due 12:58 will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:23
11:36 London Paddington to Hereford due 15:04 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:24
12:36 London Paddington to Hereford due 16:04 will be reinstated.
It will be started from Worcester Shrub Hill.
This is due to a shortage of train crew.
Last Updated:24/11/2024 05:01
15:36 London Paddington to Great Malvern due 18:15 will be terminated at Oxford.
This is due to a shortage of train crew.
Last Updated:24/11/2024 03:00
16:36 London Paddington to Great Malvern due 19:15 will be started from Reading.
This is due to a shortage of train crew.
Last Updated:24/11/2024 05:08
20:36 London Paddington to Worcester Shrub Hill due 23:00 will be cancelled.
This is due to a shortage of train crew.
Last Updated:24/11/2024 07:32
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 16:26, 23rd November 2024 |
Saturday November 23 was going well until
1W25 12:53 London Paddington to Worcester Foregate St departed +15, arrived Shrub Hill +19 and didn't make it to Foregate St.
1W27 13:50 London Paddington to Great Malvern ran OK
14:52 London Paddington to Great Malvern due 17:14 will no longer call at Hanborough, Kingham, Honeybourne, Pershore and Worcestershire Parkway Hl.
This is due to a fault with the signalling system.
Last Updated:23/11/2024 15:14
Departed Paddington +29, arrived (after skipping stations) +18.This is due to a fault with the signalling system.
Last Updated:23/11/2024 15:14
1W03 16:51 London Paddington to Hereford departed +13, arrived Great Malvern +46 and was cancelled thereafter.
20:03 Worcester Foregate Street to London Paddington due 22:38 will be started from Worcester Shrub Hill.
This is due to train crew being delayed by service disruption.
Last Updated:23/11/2024 19:32
20:20 Hereford to London Paddington due 23:37 will be started from Great Malvern.
This is due to a shortage of train crew.
Last Updated:23/11/2024 19:05
This is due to train crew being delayed by service disruption.
Last Updated:23/11/2024 19:32
20:20 Hereford to London Paddington due 23:37 will be started from Great Malvern.
This is due to a shortage of train crew.
Last Updated:23/11/2024 19:05
Re: North Cotswold Line delays and cancellations - 2024 Posted by ChrisB at 12:33, 23rd November 2024 |
Migfht have been on that train on its previous (previous night's?) journey maybe?
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 17:12, 22nd November 2024 |
2E77 05:10 Oxford to Worcester Shrub Hill (06:15) was cancelled "due to passengers causing a disturbance on this train".
There are passengers (disturbing ones at that) leaving Oxford for Worcester at 05.10? I'm not entirely sure I believe that.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Richard Fairhurst at 16:06, 22nd November 2024 |
2E77 05:10 Oxford to Worcester Shrub Hill (06:15) was cancelled "due to passengers causing a disturbance on this train".
There are passengers (disturbing ones at that) leaving Oxford for Worcester at 05.10? I'm not entirely sure I believe that.
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 06:54, 22nd November 2024 |
And after a good day on Thursday November 21 (no cancellations, one piece of late running)...
Friday November 22
2E77 05:10 Oxford to Worcester Shrub Hill (06:15) was cancelled "due to passengers causing a disturbance on this train".
Leading to
07:00 Worcester Shrub Hill to Didcot Parkway due 08:46 will be cancelled.
This is due to passengers causing a disturbance on a train.
Last Updated:22/11/2024 05:48
This is due to passengers causing a disturbance on a train.
Last Updated:22/11/2024 05:48
Meanwhile
05:53 London Paddington to Great Malvern due 08:38 will no longer call at Reading, Hanborough, Kingham, Honeybourne, Pershore and Worcestershire Parkway Hl.
It is being delayed at London Paddington.
This is due to this train being late from the depot.
Last Updated:22/11/2024 06:20
38 late from Paddington.It is being delayed at London Paddington.
This is due to this train being late from the depot.
Last Updated:22/11/2024 06:20
Cutting out the stops got it to Shrub Hill +31, cancelled thereafter.
08:56 Great Malvern to London Paddington due 11:24 will be started from Worcester Shrub Hill.
It will no longer call at Great Malvern, Malvern Link and Worcester Foregate Street.
This is due to earlier engineering works not being finished on time.
Last Updated:22/11/2024 07:55
It will no longer call at Great Malvern, Malvern Link and Worcester Foregate Street.
This is due to earlier engineering works not being finished on time.
Last Updated:22/11/2024 07:55
Re: North Cotswold Line delays and cancellations - 2024 Posted by Worcester_Passenger at 07:16, 21st November 2024 |
Wednesday November 20
The 'halts' train, 2E14 17:04 Didcot Parkway to Moreton-in-Marsh, and return, 2E16 18:51 Evesham to Oxford, cancelled "cancelled due to a problem with the traction equipment (MD)", according to RTT.
1W41 20:52 London Paddington to Great Malvern cancelled throughout "due to an issue with the train crew (TH)".