« Reply #1485 on: January 18, 2022, 15:39:29 » |
|
Whilst a partial opening will no doubt be ultimately achieved, hopefully this year, I am very doubtful as to the longer term reliability of this railway. Apart from the general issues of anything new tending towards greater complexity and reduced reliability, there seems to be a particular built in problem in this railway.
My understanding is that two different signaling systems are used, one for the core section and one for the outer bits. Both systems have to interface with the computer systems on the train. If the changeover between these two systems does not work as intended then the brakes are automatically applied
I agree that having more than one signalling system adds to the complexity, and I am sure there will be issues cropping up now and again. However: 1) Don’t the Thameslink Class 700s change signalling systems when they go through their core section which uses ATO▸ ? Do we hear of many problems with them? 2) During the extensive testing programme for Crossrail, units are regularly changing signalling modes in real life now whilst coming on and off Old Oak Common depot to get to Royal Oak. The Thameslink class 700 in the core do use ATO based on a NR» form of ETCS▸ which is different to Crossrail core which uses a system based on the same system as the Northern line. The Thameslink core also has conventional signalling and PoSA -Proceed-on-Sight Authority. One of the main integrators of the systems on Crossrail is Siemens Transportation, I saw the Crossrail system in a Siemens UK▸ factory during its factory acceptance testing a few years ago, the level of inter company cooperation is extremely high, none of the companies want or can afford reputationally for Crossrail to fail technically
|
|
|
Logged
|
Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
|
|
|
broadgage
|
|
« Reply #1486 on: January 18, 2022, 19:38:52 » |
|
I agree that having more than one signalling system adds to the complexity, and I am sure there will be issues cropping up now and again. However:
1) Don’t the Thameslink Class 700s change signalling systems when they go through their core section which uses ATO▸ ? Do we hear of many problems with them?
2) During the extensive testing programme for Crossrail, units are regularly changing signalling modes in real life now whilst coming on and off Old Oak Common depot to get to Royal Oak.
The Thameslink class 700 in the core do use ATO based on a NR» form of ETCS▸ which is different to Crossrail core which uses a system based on the same system as the Northern line. The Thameslink core also has conventional signalling and PoSA -Proceed-on-Sight Authority. One of the main integrators of the systems on Crossrail is Siemens Transportation, I saw the Crossrail system in a Siemens UK▸ factory during its factory acceptance testing a few years ago, the level of inter company cooperation is extremely high, none of the companies want or can afford reputationally for Crossrail to fail technically [/quote] Whilst that all sounds very reassuring, ISTR▸ rather similar reassurances about the failed IET▸ project. Things like various "essential requirements" regarding time to couple and uncouple, and resistance to waves at Dawlish. And testing so as to ensure reliability in service. And all "trains from London that need to be full length, will be" Guaranteed availability, with heavy penalties payable for any shortfalls. And we have seen how that has ended, even if partly hidden by/blamed upon the pandemic. So I do not share the optimism expressed by some.
|
|
|
Logged
|
A proper intercity train has a minimum of 8 coaches, gangwayed throughout, with first at one end, and a full sized buffet car between first and standard. It has space for cycles, surfboards,luggage etc. A 5 car DMU▸ is not a proper inter-city train. The 5+5 and 9 car DMUs are almost as bad.
|
|
|
TonyK
Global Moderator
Hero Member
Posts: 6594
The artist formerly known as Four Track, Now!
|
|
« Reply #1487 on: January 18, 2022, 20:09:05 » |
|
Whilst that all sounds very reassuring, ISTR▸ rather similar reassurances about the failed IET▸ project. Things like various "essential requirements" regarding time to couple and uncouple, and resistance to waves at Dawlish. And testing so as to ensure reliability in service. And all "trains from London that need to be full length, will be" Guaranteed availability, with heavy penalties payable for any shortfalls.
And we have seen how that has ended, even if partly hidden by/blamed upon the pandemic. So I do not share the optimism expressed by some.
None of which has more than a tenuous link to the matter of signalling on Crossrail.
|
|
|
Logged
|
Now, please!
|
|
|
broadgage
|
|
« Reply #1488 on: January 18, 2022, 21:06:09 » |
|
The connection is indeed tenuous, but both are large, complex and expensive railway projects. One of which has gone orribly wrong.
|
|
|
Logged
|
A proper intercity train has a minimum of 8 coaches, gangwayed throughout, with first at one end, and a full sized buffet car between first and standard. It has space for cycles, surfboards,luggage etc. A 5 car DMU▸ is not a proper inter-city train. The 5+5 and 9 car DMUs are almost as bad.
|
|
|
IndustryInsider
|
|
« Reply #1489 on: January 18, 2022, 21:12:05 » |
|
The connection is indeed tenuous, but both are large, complex and expensive railway projects. One of which has gone orribly wrong.
My mistake for thinking you were wanting to discuss a different topic, rather than just working out a way to bring it round to one of your old favourites. Tedious rather than tenuous.
|
|
|
Logged
|
To view my GWML▸ Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
|
|
|
Electric train
|
|
« Reply #1490 on: January 19, 2022, 09:18:16 » |
|
The connection is indeed tenuous, but both are large, complex and expensive railway projects. One of which has gone orribly wrong.
My mistake for thinking you were wanting to discuss a different topic, rather than just working out a way to bring it round to one of your old favourites. Tedious rather than tenuous. Crossrail is a complex project, it will have teething problems when it enters public use, just as TLP was a complex project and had teething problems. I would not say that IEP▸ is a failed project. Crossrail for the Thames Valley and Thames Estuary rail users will be a game changer for accessing the West End, City, Docklands and Heathrow; add to the mix interchange at Farringdon with Thameslink
|
|
|
Logged
|
Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
|
|
|
CyclingSid
|
|
« Reply #1491 on: January 25, 2022, 14:47:05 » |
|
|
|
|
Logged
|
|
|
|
grahame
|
|
« Reply #1492 on: January 27, 2022, 07:59:30 » |
|
Opening March, May or June (yes, 2022!) From New Civil EngineerCrossrail Ltd has earmarked March 2022 as the earliest the Elizabeth line could open to passengers, with June 2022 recorded as the latest possible opening date. A third possible opening date of May 2022 is also included in Crossrail Ltd’s latest target opening scenarios. All three dates are within the previously declared opening window of the first half of 2022.
Waiting for Bond Street to be ready would mean that the March date would be highly unlikely, with May or June a more realistic target date.
A decision on Bond Street was due to be made at a “Go/No Go meeting” scheduled for 2 December. However, according to Jacobs latest PREP [project representative] report, that meeting was delayed until an unidentified date in January.
|
|
|
Logged
|
Coffee Shop Admin, Chair of Melksham Rail User Group, TravelWatch SouthWest Board Member
|
|
|
Electric train
|
|
« Reply #1493 on: January 27, 2022, 13:18:22 » |
|
Opening March, May or June (yes, 2022!) From New Civil EngineerCrossrail Ltd has earmarked March 2022 as the earliest the Elizabeth line could open to passengers, with June 2022 recorded as the latest possible opening date. A third possible opening date of May 2022 is also included in Crossrail Ltd’s latest target opening scenarios. All three dates are within the previously declared opening window of the first half of 2022.
Waiting for Bond Street to be ready would mean that the March date would be highly unlikely, with May or June a more realistic target date.
A decision on Bond Street was due to be made at a “Go/No Go meeting” scheduled for 2 December. However, according to Jacobs latest PREP [project representative] report, that meeting was delayed until an unidentified date in January. In the Jan 22 update from Mark Wild CEO▸ of Crossrail Bond Street stats it has been "decoupled" from the opening of the railway in this video at 2min 54 sec https://www.youtube.com/watch?v=ZnVeE8DxTzk is where he mentions it. Having been involved in Thameslink and the opening of a new section of that (Canal Tunnels) and the impact it had on the already operational railways, I know there is a well structured and rigorous safety verification process that involves all the 'stake holders' (Police both BTP▸ and civil, Fire and Rescuce, ambulance, service, local authorities, other railway infrastructure operators etc) TfL» DfT» etc and of course the ORR» The process is not an overnight one the evidence will have been verified as the pre opening testing was going on. March might be a big ask, Easter school holidays I would say is nearer date and defiantly in time for Queen Platinum Jubilee
|
|
|
Logged
|
Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
|
|
|
TonyK
Global Moderator
Hero Member
Posts: 6594
The artist formerly known as Four Track, Now!
|
|
« Reply #1494 on: January 29, 2022, 21:48:05 » |
|
Opening March, May or June (yes, 2022!)
The first fare-paying passenger from Abbey Wood to Paddington has already been carried according to ITV News. Crossrail security breach as passenger travels by mistake on test train to Paddington
Wednesday 26 January 2022, 3:46pm
London transport bosses investigated a serious security breach on Crossrail after a member of the public travelled on a test train by mistake.
The passenger got on board at Abbey Wood in south east London and travelled through the new tunnels to Paddington.
Platforms are meant to be out of bounds to the public but Crossrail boss Howard Smith said the man wandered through an open gate.
"Abbey Wood station is used by Southeastern trains, it's open, it's been built for several years," said Howard Smith.
"But the Elizabeth Line platforms should be closed off with a gate.
"The gate used by drivers to get to and from the trains was left open and a passenger innocently came down to the platform and boarded the train that they saw was marked Paddington which is where they wanted to go.
"As soon as they got off the train they were picked up by staff.
"They conducted an investigation and changed the arrangements regarding the gate keeping it locked and with regard to signage," Mr Smith added.
|
|
|
Logged
|
Now, please!
|
|
|
TaplowGreen
|
|
« Reply #1495 on: January 30, 2022, 08:11:53 » |
|
That's an absolutely shocking breach of security.
If someone with evil intent had been able to just breeze through in that manner God knows what the consequences could have been.
|
|
|
Logged
|
|
|
|
IndustryInsider
|
|
« Reply #1496 on: January 30, 2022, 10:38:03 » |
|
Not great I grant you, but mountains out of molehills if you ask me. It’s not as if they spent the whole day roaming the tunnels and stations at will. They snuck through a gate onto a train and got picked up when they got off at the other end.
I’d have thought someone with ‘evil intent’ would be better off waiting until it was properly open…or get a job actually working on the project?
|
|
|
Logged
|
To view my GWML▸ Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
|
|
|
TaplowGreen
|
|
« Reply #1497 on: January 30, 2022, 15:05:32 » |
|
Not great I grant you, but mountains out of molehills if you ask me. It’s not as if they spent the whole day roaming the tunnels and stations at will. They snuck through a gate onto a train and got picked up when they got off at the other end.
I’d have thought someone with ‘evil intent’ would be better off waiting until it was properly open…or get a job actually working on the project?
I wish I could feel so casual about it, but having been involved in two near misses myself (Irish and Islamist terrorist incidents), it's difficult.
|
|
|
Logged
|
|
|
|
IndustryInsider
|
|
« Reply #1498 on: January 30, 2022, 15:38:20 » |
|
I was at Paddington when the Edgware Road bomb went off. A working tube line of course, which was my point really.
|
|
|
Logged
|
To view my GWML▸ Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
|
|
|
stuving
|
|
« Reply #1499 on: January 30, 2022, 16:35:11 » |
|
The train schedule loaded for today was for a test of 24 tph from Westbourne Park through the tunnel to various other ends. Not continuous, each way had about half of each hour at full rate, but in the event it was never sustained for even half an hour. Some attempt was kept up at running as many as possible until lunchtime, when they gave up. No doubt it was all a valuable learning experience.
I did wonder if the complete lack of trains in the tunnel meant the information feed had failed. But there is now a something going through - 5L80, which changed into 5C80 at Paddington Crossrail. That, however, is an inter-depot transfer from west to east, and I think that's why it gets a 5xxx ID.
|
|
|