P7/8/9 sequencing has been mentioned before, but probably deserves another discussion. The main reason being because I think until only a few months ago no-one was really aware of the temporary platform plan, early references were usually to it just 'closing'...
I think though, that the existing P7 really has to close to finish its roof and its remaining connecting sections up to the transfer deck - these cannot be built over the existing tracks, and they cannot easily add all the main steelwork with the platform in public use.
The way they are temporarily 'moving' P7 now therefore allows for it being properly available again from some time after Christmas. P8 and P9 won't ever fully close, and I have been assured they will always remain at least partly available during the working weeks although there will be periods with one or other's overall length curtailed to about a 6 car length.
So if P8/9 never actually close, they don't really provide a worthwhile reason not to start P7 now. Basically, they are doing it now because they can, and any delay would delay the station area part of the overall project.
PS FGW▸ 's website description of the works does include this bit:
Works to upgrade platforms 8 and 9 will take place simultaneously. To ensure minimum disruption to customers, the platforms will remain in use while the phased upgrade works are carried out. Platforms 8&9 are due to complete by late spring 2014.
We are also now suggesting that when P7 re-opens it will be almost full length, certainly allowing for
HSTs▸ - and that suggests that the final area to be worked on will be just the old gateline area and new overall roof by platforms 4/5/6.
Another point that's just occurred to me, is that we don't know the full sequencing of the track layout alterations to bring the main viaduct, the 'festival line' (
XC▸ underpass) and the 'feeder lines' (Freight and Up Westbury underpass) into use - it's possible that the route through P7 will be more important at some stage in a future transitional period. I'm sure they'll have a cunning plan. It isn't inconceivable that they'll eventually need to use P7 for more XC reversals because they can no longer use P9 for those trains, although P9 would probably remain in use for down main trains towards Didcot.
Meanwhile though, I don't think the timing of the P10 rebuild has a huge impact on the down service at all, so it is possibly of little relevance to your main question.
Paul