« Reply #435 on: March 17, 2022, 10:57:34 » |
|
Yes, that’s right Paul. Even some of the signals already have route indications into what will become Platform 5.
There are some new high speed S&C▸ ’s going in between the Walton Well Road bridge and Oxford North Junction as well, but again, signals are already ready and waiting for that.
The Sheepwash bridge replacement at the north end of the station will be quite a big project, but nothing compared to the Botley Road bridge works.
|
|
|
Logged
|
To view my GWML▸ Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
|
|
|
paul7575
|
 |
« Reply #436 on: March 17, 2022, 11:52:01 » |
|
Yes, that’s right Paul. Even some of the signals already have route indications into what will become Platform 5.
There are some new high speed S&C▸ ’s going in between the Walton Well Road bridge and Oxford North Junction as well, but again, signals are already ready and waiting for that.
The Sheepwash bridge replacement at the north end of the station will be quite a big project, but nothing compared to the Botley Road bridge works.
I was fairly sure that would be the case; I also thought you’d posted a track layout including P5 somewhere, but I’m not having much success finding it… Paul
|
|
|
Logged
|
|
|
|
IndustryInsider
|
 |
« Reply #437 on: March 17, 2022, 12:25:48 » |
|
I was fairly sure that would be the case; I also thought you’d posted a track layout including P5 somewhere, but I’m not having much success finding it…
I’ll try and repost it later.
|
|
|
Logged
|
To view my GWML▸ Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
|
|
|
stuving
|
 |
« Reply #438 on: March 17, 2022, 12:57:49 » |
|
I was fairly sure that would be the case; I also thought you’d posted a track layout including P5 somewhere, but I’m not having much success finding it…
I’ll try and repost it later. There was this earlier post, and an NR» presentation that's hard to interpret now (not just because it's fuzzy). But I vaguely recall some diagrams showing the phasing more clearly. Maybe that was in another thread, not one of the three I've found?
|
|
|
Logged
|
|
|
|
paul7575
|
 |
« Reply #439 on: March 17, 2022, 16:19:13 » |
|
Thanks stuving, I didn’t go back searching anything like as far as 2013, to find the “earlier post”, doesn’t time fly...
I did see that link to an NR» presentation but haven’t tried to open it, they seem to want some sort of log-in.
|
|
|
Logged
|
|
|
|
stuving
|
 |
« Reply #440 on: March 17, 2022, 17:53:38 » |
|
Thanks stuving, I didn’t go back searching anything like as far as 2013, to find the “earlier post”, doesn’t time fly...
I did see that link to an NR» presentation but haven’t tried to open it, they seem to want some sort of log-in.
I think an account is required only for download, and there is an in-page viewer. As it's Scribd, you may prefer not to create an account.
|
|
|
Logged
|
|
|
|
paul7575
|
 |
« Reply #441 on: March 17, 2022, 18:26:41 » |
|
It’s now opening the in-page viewer on my iPad, it wasn’t an hour ago. 
|
|
|
Logged
|
|
|
|
IndustryInsider
|
 |
« Reply #442 on: March 20, 2022, 22:36:05 » |
|
I have a copy of the Signal Plans for this phase of the project. Can’t share here or distribute them, but happy to answer any questions about the revisions to the track and signalling as a result.
|
|
|
Logged
|
To view my GWML▸ Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
|
|
|
stuving
|
 |
« Reply #443 on: June 23, 2022, 12:58:33 » |
|
The Transport for Works Order is expected to be signed off before the summer & application to the DfT» for funding soon after..
... but in reality, the TWAO▸ for OSP2 was granted yesterday, published by DfT. This is "Land Only", as most of the actual work is permitted development. Some things require a sort of approval (can't be refused) by the planning authority, and wasn't there one for the Botley Road Bridge? Or was that just a plan ... it's easy to get lost following this project! We did miss Oxford City's approval of the design aspects of the station entrance last November.
|
|
|
Logged
|
|
|
|
stuving
|
 |
« Reply #444 on: August 07, 2022, 13:14:43 » |
|
There was an item last week in the Oxford Mail about a long closure of Oxford station next summer. When looked at more closely, the message is that the real news will be announced at the end of August - which I guess means "don't believe what I've said here". This is the bit that sounds a bit scary: The Botley Road rail bridge will need to be replaced as part of Network Rail’s plans to increase capacity at the station, with this leading to the closure of the road.
While timings on how long the closure will last are unconfirmed, it is believed that it could be approximately three months.
A spokesperson for Network Rail told the Oxford Mail that both Botley Road and the station will be closed next summer, either at the end of July or start of August.
Network Rail says plans are set to be finalised towards the end of this month.
Lines in and out the station are already set to be closed over four weekends in September and October, to allow the second phase of works to increase capacity.
This is currently set for the weekends of September 10-11, 17-18, and 24-25, plus October 1-2. Now, I'm not sure whether a station being completely closed means no trains through it, or just no passengers. In any case, it does sound rather extreme. Closing Botley Road for that long perhaps - particularly if, for example, it makes it possible to prop up the railway while a new bridge is built. At the moment, the 2023 EAS» includes a couple of weekend closures in the spring, plus more than a month of Sundays, and a 9-day blockade at the end of July. That presumably is what is being nailed down within NR» and the Oxford councils at the moment.
|
|
|
Logged
|
|
|
|
|
ellendune
|
 |
« Reply #446 on: August 07, 2022, 17:56:51 » |
|
Usually in these cases the road closure is significantly longer than the rail closure so I am guessing that Botley Road will be closed for 3 months but the rail closures will only be as in the EAS» .
|
|
|
Logged
|
|
|
|
stuving
|
 |
« Reply #447 on: August 07, 2022, 20:35:15 » |
|
Usually in these cases the road closure is significantly longer than the rail closure so I am guessing that Botley Road will be closed for 3 months but the rail closures will only be as in the EAS» .
Last year, NR» were saying even a Botley Road closure of five days would be enough. That was for trundling in a new bridge deck, but I guess the work on the road is not really theirs to do or to make statements about. The first bit of this phase of work starts next month, with four weekend closures of the railway through Oxford, mainly (I think) to insert new high-speed crossovers. Oxford area – weekends of 10/11, 17/18, 24/25 September and 1/2 October
No train services to/from Oxford.
Rail improvement work will affect trains between Didcot Parkway, Oxford and Hanborough.
This work will also affect CrossCountry trains between Banbury, Oxford and Didcot Parkway, plus Chiltern Railways trains between Oxford Parkway and Oxford. ( More details)
|
|
« Last Edit: August 17, 2022, 13:32:46 by stuving »
|
Logged
|
|
|
|
ChrisB
|
 |
« Reply #448 on: August 07, 2022, 20:56:43 » |
|
Yes, three high-speed crossovers at North Oxford Junction. Sort of surprised that services to/from the south are completely removed. As both through platforms are totally reversable, I’d have expected the half-hourly fasts PAD» /OXF» to be anle to run which wiuld have reduced the number of buses.
But I suspect with possible industrial action, getting sufficient buses booked for the whole bustitution was sensible. I wonder now though, should indistrial action take place across any of those weekends, whether the bustitution will still go ahead. They don’t bustitute any other services (understandably)
|
|
|
Logged
|
|
|
|
ellendune
|
 |
« Reply #449 on: August 07, 2022, 22:09:47 » |
|
Usually in these cases the road closure is significantly longer than the rail closure so I am guessing that Botley Road will be closed for 3 months but the rail closures will only be as in the EAS» .
Last year, NR» were saying even a Botley Road closure of five days would be enough. That was for trunding in a new bridge deck, but I guess the work on the road is not really theirs to do or to make statements about. Having looked at the scale of the work proposed. Reducing the level of the road and widening it. I would be astounded if anyone thought it possible to do it with a 5 day road closure. I didn't think the road was wide enough to work on half the road with traffic signals.
|
|
|
Logged
|
|
|
|
|