with I believe through Paddington - Reading electrics locals in the September timetable.
So soon? I was led to believe (through unofficial sources mind) that services would start on Jan 2nd, which would include running through to Didcot.
That's what I understand too....
Given the complexity of the Reading station layout and the need to prove it all, not to mention training drivers and staff, I'd be very surprised if there were only a month between energisation and planned introduction into public service. Six months sounds more like it, perhaps the plan is to allow
ECS▸ runs from September (with the fallback position being that loco haulage will continue if there are any issues with the
OLE▸ ).
The Hendy dates for
infrastructure authorisation were:
Maidenhead to Didcot: December 2017
Didcot to Wootton Bassett Junction: December 2018
Wootton Bassett Junction to Bristol Parkway: December 2018
Reading to Newbury: December 2018
Bristol Parkway to Cardiff: December 2018
Didcot to Oxford: June 2019
Wootton Bassett Junction to Bristol Temple Meads: February 2019-April 2020
Filton Bank: Early