Bmblbzzz
|
|
« Reply #2145 on: November 09, 2016, 13:23:10 » |
|
and also the politics of serving the Welsh capital will have a bearing.
And I was just thinking to myself "It would surely be too cynical to suspect that this is partly down to post-Brexit Union-preserving politics."
|
|
|
Logged
|
Waiting at Pilning for the midnight sleeper to Prague.
|
|
|
ChrisB
|
|
« Reply #2146 on: November 09, 2016, 14:20:23 » |
|
This is the National Audit Office (NAO) view on the impact of the electrification delays on the rolling stock cascade:
{Diagram] Does ordering extra AT300's for the Oxford route suggest that the electrification is not just delayed but effectively cancelled? For this Government? Yes, I'd say so. Other facts to be noted from that diagram - - 11 HSTs▸ retained till 2018 (and 180s(?) -I thought these *had* to go at end of 2017?) - 165s & 166s staying in TV until electrification complete in CP6▸ - Bi-modes now replacing 180s & HSTs for Dec18 TT change - 2 additional AT300s also ordered to keep hourly through services to Bedwyn - 153/150s retained in West until 2018 - impact on North services - 143s in Exeter decommissioned a year later in Dec18
|
|
|
Logged
|
|
|
|
eightf48544
|
|
« Reply #2147 on: November 09, 2016, 14:44:12 » |
|
What has happened to our planning, logistics and engineering expertise?
98 years ago my grandfather helped push a numerically superior German Army out of France in just 100 days.
The planning and logistics for that were enormous 1 million men in France. They make GWML▸ electrification look trivial especially as nobody's shooting at the engineers.
|
|
|
Logged
|
|
|
|
didcotdean
|
|
« Reply #2148 on: November 09, 2016, 15:36:00 » |
|
The initial cost always smelt completely wrong to me. Sadly this has shown up that Network Rail had a poor understanding of its physical assets and capabilities and that the DfT» seemed to put its trust into it which was misplaced - although its shifting specification (if you can call it that) was significantly to blame too.
|
|
« Last Edit: November 09, 2016, 15:41:12 by didcotdean »
|
Logged
|
|
|
|
1st fan
|
|
« Reply #2149 on: November 09, 2016, 15:54:40 » |
|
This is the National Audit Office (NAO) view on the impact of the electrification delays on the rolling stock cascade:
{Diagram] Does ordering extra AT300's for the Oxford route suggest that the electrification is not just delayed but effectively cancelled? For this Government? Yes, I'd say so. Other facts to be noted from that diagram - - 11 HSTs▸ retained till 2018 (and 180s(?) -I thought these *had* to go at end of 2017?) - 165s & 166s staying in TV until electrification complete in CP6▸ - Bi-modes now replacing 180s & HSTs for Dec18 TT change - 2 additional AT300s also ordered to keep hourly through services to Bedwyn - 153/150s retained in West until 2018 - impact on North services - 143s in Exeter decommissioned a year later in Dec18 Will they have to make the HST doors automatic and all the other stuff to make them compliant with the PRM▸ -TSI regulations? I would guess the trains would meet most of the regs already but the doors would be a biggie.
|
|
|
Logged
|
|
|
|
Tim
|
|
« Reply #2150 on: November 09, 2016, 16:28:51 » |
|
The new regs only come in in 2020, so we could operate them as they are for a few years more. There is also the possibility of a temporary derogation from the regulations. This kind of temporary, unexpected delay that one might assume the derogations were designed for.
|
|
|
Logged
|
|
|
|
Tim
|
|
« Reply #2151 on: November 09, 2016, 16:32:54 » |
|
.... I think that the trains would also need scrolling LED thingies to meet the regs. There is also the matter of fitting retention toilets. Although not related to the disability regs, NR» has said that it wants track discharge to end by 2020. It is of course NR who have screwed up here so it would be kind of poetic justice if one outcome was that their infrastructure was to continue to be c**ped on (although hardly fair to the wo/man in the track gang)
|
|
|
Logged
|
|
|
|
Richard Fairhurst
|
|
« Reply #2152 on: November 09, 2016, 17:21:21 » |
|
Other facts to be noted from that diagram -
- 11 HSTs▸ retained till 2018 (and 180s(?) -I thought these *had* to go at end of 2017?) It's a particularly confusing diagram. I don't think it's saying that the 180s are being retained. That said, AIUI▸ Hull Trains' fleet of 180s isn't yet spoken for, now that they too have ordered AT300s, so there's some room for manoeuvre there...
|
|
|
Logged
|
|
|
|
grahame
|
|
« Reply #2153 on: November 09, 2016, 17:28:08 » |
|
The NAO report ( mirror) has a wealth of information ... so many things strike me ... Electrifying the line from Maidenhead to Cardiff by December 2018 relies on the assumption that Network Rail can significantly increase mast installation and piling rates, compared with the rates it has achieved so far. Network Rail’s current target is to increase the number of piles installed each week from 62 in August 2016 to 195 piles by November 2016. The rate of mast installation is expected to increase from 55 per week to 191 per week over the same period. However, Network Rail is currently developing a new plan which it expects will mean it will install around 150 piles per week between November 2016 and March 2017, without delaying the completion of electrification any further. In early September 2016 Network Rail had completed 6,804 foundations, 44% of the total required. It had installed 3,438 masts (23% of the total) and 1,352 booms (15%).
|
|
|
Logged
|
Coffee Shop Admin, Chair of Melksham Rail User Group, TravelWatch SouthWest Board Member
|
|
|
bobm
|
|
« Reply #2154 on: November 09, 2016, 17:45:33 » |
|
They make GWML▸ electrification look trivial especially as nobody's shooting at the engineers.
Without wishing to be disrespectful (my grandfather survived the First World War) perhaps it was the very fact that people were shooting at the engineers that sharpened the mind to the job in hand.
|
|
|
Logged
|
|
|
|
grahame
|
|
« Reply #2155 on: November 09, 2016, 18:37:08 » |
|
The NAO report ( mirror) has a wealth of information ... so many things strike me ... And an interesting diagram ...
|
|
|
Logged
|
Coffee Shop Admin, Chair of Melksham Rail User Group, TravelWatch SouthWest Board Member
|
|
|
Adelante_CCT
|
|
« Reply #2156 on: November 09, 2016, 18:50:06 » |
|
perhaps it was the very fact that people were shooting at the engineers that sharpened the mind to the job in hand.
What are you suggesting bobm?
|
|
|
Logged
|
|
|
|
simonw
|
|
« Reply #2157 on: November 09, 2016, 19:48:15 » |
|
The NAO report ( mirror) has a wealth of information ... so many things strike me ... And an interesting diagram ... Looking at the map, it would be interesting to know which parts carry the most traffic, passengers and trains. I am not convinced that taking electrification of the line to Cardiff is more economically sensible than Bristol.
|
|
|
Logged
|
|
|
|
Bmblbzzz
|
|
« Reply #2158 on: November 09, 2016, 19:49:42 » |
|
The NAO report ( mirror) has a wealth of information ... so many things strike me ... Electrifying the line from Maidenhead to Cardiff by December 2018 relies on the assumption that Network Rail can significantly increase mast installation and piling rates, compared with the rates it has achieved so far. Network Rail’s current target is to increase the number of piles installed each week from 62 in August 2016 to 195 piles by November 2016. The rate of mast installation is expected to increase from 55 per week to 191 per week over the same period. However, Network Rail is currently developing a new plan which it expects will mean it will install around 150 piles per week between November 2016 and March 2017, without delaying the completion of electrification any further. In early September 2016 Network Rail had completed 6,804 foundations, 44% of the total required. It had installed 3,438 masts (23% of the total) and 1,352 booms (15%). For a second I thought "electrification from Kent to Wales!" I do sometimes get Maidenhead and Maidstone mixed up...
|
|
|
Logged
|
Waiting at Pilning for the midnight sleeper to Prague.
|
|
|
stuving
|
|
« Reply #2159 on: November 09, 2016, 19:57:01 » |
|
Looking at the map, it would be interesting to know which parts carry the most traffic, passengers and trains.
I am not convinced that taking electrification of the line to Cardiff is more economically sensible than Bristol.
I think you're missing the point. The map just shows where the work that the NAO report was about was, as originally proposed, to be done. Cardiff is proceeding because its end date is in CP5▸ . Bristol isn't, as is has already been delayed by the resignalling work and can't be done in CP5. That's confirmed in the report to be the reason: The Department has instructed Network Rail to defer electrification on some stretches of the route for longer, reflecting between £146 million and £165 million of spending, because it cannot meet the costs within the current funding package. It still intends to electrify these sections, during the next rail investment period, which runs from April 2019 to March 2024. As a result, passengers in affected areas may have to wait longer to see the full benefits of modernisation. These deferrals are intended to fund projects that are considered critical, but were not allocated funding in the 2015 replan. Such critical projects account for £72 million of the funding shortfall. The largest of these are: - A new depot in Exeter (£36 million). The Department agreed to make funding
available for this in March 2015, as part of the second franchise extension, known as a ‘direct award’. - Work at Bristol East Junction (£15 million). Network Rail now expect that it will
need to spend more on this project in the current rail investment period in order to complete it before this section of line is electrified. - Platform extensions on the Cotswold Line, which are needed to allow the new
Intercity Express Programme trains to stop at smaller stations (£13 million). The Department instructed Network Rail to carry out this work in August 2014.
|
|
|
Logged
|
|
|
|
|