I took a late night trip out from Paddington last night and I've never seen so much activity. Pretty much constant (wo)men and machinery from West Drayton to Didcot all busy fitting and testing the various stages of works that have been reached in those areas.
The plan is apparently to have all wiring complete between Airport Jcn and Maidenhead by the end of November (2016) so the planned
EMU▸ services from Maidenhead can commence as of the May 2017 timetable.
The difficult part is getting the foundations done and the structures erected on top, the 4 track portals requiring and all lines block, not to many of the on the
GWML▸ .
Now back to this electric power stuff, what makes the Amps is the dancing pixies they dance to the tune of 50Hz
Now seriously the reason for the AT system, the concept is not new its been around for about 100 years, the Auto Transformer system of 25kv - 0 - 25kV allows the transmission of power at 50kV yet retain the use of standard
OLE▸ 25kV components such as insulators and cables.
Why 50kV? it is all to do with I
2R which is power loss in effect doubling the Voltage halves the current which has dramatic effect in reducing the power loss for the same size conductors. This allows for doubling the space between Grid supply points. If the GWML had been electrified in the 1980/90's as original planned by
BR▸ between Paddington and Reading there would have been 3 Grid supply points, Old Oak Common, Iver, and Reading, all these would have come off of the 132kV network. The largest 132/25kV transformers are 26MVA
Even in the 1980/90's the Electricity Supply Network were getting concerned over the impact of the railway large single phase loading, the
ECML▸ had to have a number of addition Feeder Stations added on the railway even though the 25kV supply came from the same Grid point, Grantham and Newark are examples of this, it was done to even the load on the 132kV network.
The GWML now has 3 Grid supply points between Paddington and Bristol!! The BR classic 25kV scheme would have needed 8 or 9 and that does not include on the Berks n Hants. The supply being taken from the 400kV Grid which allows for larger transformers of 50MVA, although this increases the fault level from 6kA to 12kA. Kensal Green feed to the Mid Point at Maidenhead to Abbey Wood / Bow and Didcot Mid Point at Maidenhead to Wooton Basset (I believe), also to Oxford and Bedwyn (although if there is a service increase a new Grid supply from Bramley to Southcote Jcn is in the outline plan. Each 400kV Grid supplies approx. 50 miles in each direction.
Didcot can feed right into Paddington if need to, with the Crossrail tunnels being fed from the Bow end. I believe Didcot can even do emergency feeding into the Crossrail Tunnels although this would not be for service running.
See told you its all smoke n mirrors and dancing pixies