lordgoata
|
|
« Reply #1305 on: October 27, 2015, 11:36:17 » |
|
Hi all, In case anyone is interested, someone placed a FOI▸ request for all correspondance between the Goring & South Stoke Rail Action Group, and South Oxfordshire District Council back at the end of August. There is a lot of interesting information in the emails, including meeting minutes, Q&A's and various other presentations from NR» , RAG▸ , and the magnitude of other groups that are now involved. https://www.whatdotheyknow.com/request/correspondence_with_goring_and_s_2
|
|
|
Logged
|
|
|
|
grahame
|
|
« Reply #1306 on: November 07, 2015, 02:23:42 » |
|
From Plaid Cymru https://www.partyof.wales/news/2015/11/06/rail-electrification-to-swansea-faces-delay-plaid-cymru-understands/?force=1Rail electrification to Swansea faces delay, Plaid Cymru understands
Electrification of the main rail line between Cardiff and Swansea could slip by up to five years, Plaid Cymru has learnt.
Well-placed rail industry sources have told the Party of Wales that the Swansea leg could slip into Network Rail^s next Control Period running from April 2019 to March 2024. It was originally scheduled to take place during the current Control Period running to March 2019.
It is understood the slippage is as a result of a backlog of Network Rail works and a cut in funding.
This summer UK▸ Government ministers admitted that the electrification of the line to Swansea may be pushed back beyond 2018.
Plaid Cymru^s Shadow Transport Minister, Rhun ap Iorwerth AM, said: "A review of the existing Network Rail Control Period is due to be published in the next few weeks.
"The message I^m hearing is that there are real fears that we will face a delay in electrification between Cardiff and Swansea of between one and five years, as it will fall into a new Control Period.
"Short-changing the people of Swansea would be totally unacceptable and I call on the UK Government to give a firm commitment on the timetable for electrification to our second city. and "This uncertainty has not been helped by the UK Government reneging on the prioritising of South Wales electrification."
Hmm ... I would rather suspect it's not a change of priorities but rather an element of what the review will signal.
|
|
|
Logged
|
Coffee Shop Admin, Chair of Melksham Rail User Group, TravelWatch SouthWest Board Member
|
|
|
Rhydgaled
|
|
« Reply #1307 on: November 07, 2015, 09:21:46 » |
|
Hmm ... I would rather suspect it's not a change of priorities but rather an element of what the review will signal. The GWML▸ electrification would seem to be the government's main priority for electrification, given it was the one that wasn't 'paused' earlier this year. Thus, unless Sir Peter Hendy's presents a very strong argument for re-prioritising something else ahead of parts of the GWML scheme it would seem logical for Cardiff-Swansea to follow immediately after London-Cardiff/Bristol/Oxford. Thus, unless the schedule-slip is absolutly huge I would hope it won't take until 2024 to complete. It might slip into the begining of CP6▸ though, Dec 2020 maybe? I'm not in the rail industry though so I'm not clear just how delayed the scheme is.
|
|
|
Logged
|
---------------------------- Don't DOO▸ it, keep the guard (but it probably wouldn't be a bad idea if the driver unlocked the doors on arrival at calling points).
|
|
|
didcotdean
|
|
« Reply #1308 on: November 07, 2015, 10:07:53 » |
|
There are though a lot of projects that have been 'agreed' and funded to the level that was indicated to be necessary by Network Rail, and are incorporated into the plans of local authorities etc, some of which are part-funding the development itself, or other developments on the periphery. East-West rail is one example, and I daresay the electrifications all are including TPE▸ and MML» .
The credibility of Network Rail will sink greatly locally, whichever of these may be de-prioritised and especially if this is a multi-year delay.
|
|
|
Logged
|
|
|
|
TaplowGreen
|
|
« Reply #1309 on: November 07, 2015, 10:32:53 » |
|
The credibility of Network Rail will sink greatly locally, whichever of these may be de-prioritised and especially if this is a multi-year delay.
.........maybe they could consider a rebranding exercise, seems quite popular at the moment amongst rail organisations whose credibility has sunk!
|
|
|
Logged
|
|
|
|
didcotdean
|
|
« Reply #1310 on: November 07, 2015, 10:46:36 » |
|
That might be as a result of privatisation
|
|
|
Logged
|
|
|
|
Gordon the Blue Engine
|
|
« Reply #1311 on: November 07, 2015, 15:59:33 » |
|
Hi all, In case anyone is interested, someone placed a FOI▸ request for all correspondance between the Goring & South Stoke Rail Action Group, and South Oxfordshire District Council back at the end of August. There is a lot of interesting information in the emails, including meeting minutes, Q&A's and various other presentations from NR» , RAG▸ , and the magnitude of other groups that are now involved. https://www.whatdotheyknow.com/request/correspondence_with_goring_and_s_2This is a significant issue and I^m surprised it hasn^t had more publicity. It has the potential to delay train testing and could prompt similar protest action down the line where there are AONB▸ 's and listed structures etc. I think the OHLE is more intrusive than it need be ^ it looks like standard length uprights are being used which project well above (to varying degrees) the horizontal spans, which looks ugly. It would look much neater if the uprights were cut level with the horizontals as in previous electrification schemes. Or maybe this will happen after final installation and alignment etc?
|
|
|
Logged
|
|
|
|
paul7575
|
|
« Reply #1312 on: November 07, 2015, 16:20:14 » |
|
I think the OHLE is more intrusive than it need be ^ it looks like standard length uprights are being used which project well above (to varying degrees) the horizontal spans, which looks ugly. It would look much neater if the uprights were cut level with the horizontals as in previous electrification schemes.
The 'excess height' is not really removable, it is there to carry the 25 kV auto transformer feeders. Paul
|
|
|
Logged
|
|
|
|
Oberon
|
|
« Reply #1313 on: November 07, 2015, 17:12:02 » |
|
I seem to remember when the ECML▸ was electrified in the 1980s it happened very quickly and came out under initial cost projections. I'm sure I read BR▸ gave quite a lot of money back to the government after the scheme had been completed. So the question must be asked, if BR did it so efficiently twenty odd years ago, why is Network Rail now making such a complete hash of electrification on the GW▸ ? In those days we had an anti-rail government and a relatively efficient railway, these days it seems to be something like the opposite state of affairs. It's all very sad
|
|
|
Logged
|
|
|
|
SandTEngineer
|
|
« Reply #1314 on: November 07, 2015, 18:42:47 » |
|
The biggest problem is of course that Network Rail cannot cope and this has been brought about by a significant loss of skills due to the way it treats its people and the lack of experienced leadership.
I think I have mentioned before elsewhere on this forum that perhaps is now the time to split NR» so that it becomes solely a maintenance and operating company and hand over all new works and renewals to some of the experienced Project Management companies with worldwide knowledge of significant infrastructre building (Atkins, Bectel etc.) All you need is a very robust Handover/Handback process. Many large projects in the past have been handled this way (WCML▸ Four Tracking, HS1▸ , Reading Station Reconstruction and Remodelling).
I would cite Crossrail as a current example of a very significant infrastructure project that is (fairly) quietly progressing in the background without the issues that NR has suffered.
|
|
« Last Edit: November 07, 2015, 18:49:14 by SandTEngineer »
|
Logged
|
|
|
|
Rhydgaled
|
|
« Reply #1315 on: November 07, 2015, 21:24:10 » |
|
hand over all new works and renewals to some of the experienced Project Management companies with worldwide knowledge of significant infrastructre building (Atkins, Bectel etc.) All you need is a very robust Handover/Handback process. Many large projects in the past have been handled this way (WCML▸ Four Tracking, HS1▸ , Reading Station Reconstruction and Remodelling). I thought the GWML▸ electrification had been subcontracted to recognised names anyway, perhaps not Atkins specificly though. I would cite Crossrail as a current example of a very significant infrastructure project that is (fairly) quietly progressing in the background without the issues that NR» has suffered. Good point, while some rail infrustructure projects in the UK▸ are in disarray others do appear to be going fairly smoothly. For (possibly) another example, I can't recall any hicups with the new Borders railway in Scotland.
|
|
|
Logged
|
---------------------------- Don't DOO▸ it, keep the guard (but it probably wouldn't be a bad idea if the driver unlocked the doors on arrival at calling points).
|
|
|
stuving
|
|
« Reply #1316 on: November 08, 2015, 00:29:36 » |
|
The GWML▸ electrification would seem to be the government's main priority for electrification, given it was the one that wasn't 'paused' earlier this year. Thus, unless Sir Peter Hendy's presents a very strong argument for re-prioritising something else ahead of parts of the GWML scheme it would seem logical for Cardiff-Swansea to follow immediately after London-Cardiff/Bristol/Oxford.
In official terminology, Project W001a is called "Great Western Electrification" but only runs to Cardiff. It is clearer to call it "Great Western Main Line Electrification", though of course the line onward to Swansea is still a main line, if not the main line. As of the last plan revision in June all its future committed dates have gone and these are now "TBC". There is a note of the Hendy review, but pending its outcome most other projects were left unchanged. The comments are about Cardiff-Swansea, which is a separate project (W001b) called "South Wales Main Line Electrification". It has never had any committed dates beyond GRIP▸ stage 3, which was April 2015 but has already been revised to September (and quite possibly missed again). It still has its original DfT» target dates and a warning about "reprofiling", as well as the overall note of the Hendy review. When the control period structure was created, there may have been some notion that NR» would be given a big (very big) heap of money for five years and left to get on with it (but with ORR» peering over their shoulders). Of course that never happened, and it is now a reporting framework, rather than a spending control one. So if something is planned for the end of CP5▸ and slips a few months, it is now in CP6▸ - but hardly an excuse for reacting as if NR are now free to decide on their own defer it for five years. Not that such details would affect politicians' willingness to make incontinent comments like Plaid Cymru's. And there is still a good reason for completing to Swansea - the SET▸ fleet ready to go there.
|
|
|
Logged
|
|
|
|
stuving
|
|
« Reply #1317 on: November 08, 2015, 01:08:55 » |
|
The biggest problem is of course that Network Rail cannot cope and this has been brought about by a significant loss of skills due to the way it treats its people and the lack of experienced leadership.
I think I have mentioned before elsewhere on this forum that perhaps is now the time to split NR» so that it becomes solely a maintenance and operating company and hand over all new works and renewals to some of the experienced Project Management companies with worldwide knowledge of significant infrastructre building (Atkins, Bectel etc.) All you need is a very robust Handover/Handback process. Many large projects in the past have been handled this way (WCML▸ Four Tracking, HS1▸ , Reading Station Reconstruction and Remodelling).
I would cite Crossrail as a current example of a very significant infrastructure project that is (fairly) quietly progressing in the background without the issues that NR has suffered.
As I understand it, Crossrail, RSAR, and other recent large projects have used variations on the "Heathrow T5" model. That means a single project management team of the overall project managers, its main contractors, and some at least of their subcontractors. The idea was to get away from the practices that had grown up in the big Civils contractors of warily dealing with other project parties at arm's length and suing each other rather than cooperating when anything went wrong. Within this alliance they are supposed to cooperate "open-book", ignoring who works for which company. The model also involves fully funding analysed risk and contingency. That means working out what can go wrong, what its impact is, including cost, and what to do in that case. It often requires either risk reduction (starting more detailed work or on-site investigations early) or setting a large contingency budget that reduces as you proceed. When judged by the cost allocated at the start, it costs a lot more to do things that way. Some of that extra cost is real (and both T5 and RSAR were very expensive), but usually the alternative is a very optimistic budget that gets greatly overspent anyway. Whether it helps a lot to contract at the whole-project level is debatable. RSAR was led by NR, in alliance with a Costain/Hochtief joint venture as main contractor. The problem seems to be more in the planning and estimating than management, and as much at lower levels in areas only NR know about (like where things are in the ground and how to keep a railway running while you work) as in things that should be off-loaded. But as there is a review into what went wrong with CP5▸ planning and budgeting going on, due to report "by Autumn 2015", maybe we should wait for it. That's the one by Colette Bowe, in case you were likely to confuse it with Sir Peter Hendy's or Nicola Shaw's.
|
|
|
Logged
|
|
|
|
TonyK
Global Moderator
Hero Member
Posts: 6594
The artist formerly known as Four Track, Now!
|
|
« Reply #1318 on: November 08, 2015, 10:22:57 » |
|
I would cite Crossrail as a current example of a very significant infrastructure project that is (fairly) quietly progressing in the background without the issues that NR» has suffered.
That raises an interesting point. Crossrail may seem to be much the more complex project, but most of the work has been underground, using tried and tested technology in what is in effect virgin ground. The TBMs and the tunnel lining borrow much from the Channel Tunnel construction amongst others, and issues that cropped up 25 years ago are no longer problems. The station buildings are an exception, of course, but London is used to having big holes dug in it. What you see is in relatively compact areas, and complaining gets you nowhere in London anyway. The GWR▸ electrification process, on the other hand, is using a HOPS train in part, which hasn't come up to expectation. If that can only work at half the rate it was supposed to do, then its part of the project will take twice as long. We know that for next time (if there is one - my guess is there will be) and can build that knowledge into forecasts if it can't be sorted any other way.
|
|
|
Logged
|
Now, please!
|
|
|
SandTEngineer
|
|
« Reply #1319 on: November 08, 2015, 10:56:37 » |
|
Back to piling for a moment....... If you follow this link http://www.networkrail.co.uk/aspx/12281.aspx it will take you to the NR» GW▸ Electrification web page where down the page there are links to local area information on piling progress etc. This includes upcoming dates of work and maps of the affected area(s). Not seen this before. Perhaps somebody has given NR a (big) kick up the backside
|
|
|
Logged
|
|
|
|
|