« Reply #1140 on: February 27, 2015, 09:31:57 » |
|
That ought to rule out IEP▸ too. It should, but the DfT» have told 'em to take 'em, so that's decided then. Oxford Stn looks like 2016 or even 2017 before DfT get around to this rebuild According to a certain FGW▸ project director who ought to know, Oxford *station* rebuild was always 2017, never 2016. The resignalling was going to be 2016, however, and that most of it has moved back also to 2017. Chiltern is trying to get a 'phase 1 resignalling' done still in 2016. Of course, the resignalling will need to be complete before the wires can go up - any track layout changes need wires above them....and they won't want to get all the machinery back soon after putting them up before any changes
|
|
|
Logged
|
|
|
|
Electric train
|
|
« Reply #1141 on: February 27, 2015, 18:47:28 » |
|
BBC» West report today that the hold-up is because of power supply problems.
Hmm...
Not surprising there's no Over Head Line
|
|
|
Logged
|
Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
|
|
|
ellendune
|
|
« Reply #1142 on: March 06, 2015, 22:32:12 » |
|
Swindon Station Footbridge http://www.networkrail.co.uk/WorkArea/DownloadAsset.aspx?id=30064794571In order to accommodate the new trains and electrification infrastructure we need to remove the redundant Swindon Station footbridge that used to serve Polaris House. In truth it may have been intended to serve polaris house, but it has never been opened. So it never did.
|
|
|
Logged
|
|
|
|
stuving
|
|
« Reply #1143 on: March 24, 2015, 19:12:17 » |
|
If you look in the DfT» 's mini-franchise outline, at what electric services start at which SLC▸ change, it is clear that they are later than the CP5▸ timetable says. I asked an FGW▸ area manager about this at the manager-bothering session at Reading today, and he confirmed that these are revised dates. We knew there was a review going on, but only Twyford-Marlow had officially been deferred (awaiting infrastructure decisions for Bourne End).
The new milsetones are very tight - any delay in handing over working wires will jeopardise the full IEP▸ (and son of IEP) service in December 2018. There may be a little leeway in the phasing, and a priority list of what might be allowed to slip a little - I suggested that the branches, and South Wales past Cardiff, might be a few months late and found that was a familiar concept. But note - any of these dates before Dec 2018 may slip back to Dec 2018.
To Newbury, Oxford, the CP5 date (for "First Electric Train") is Dec 2016 and now it is May 2017. To Chippenham, Bristol Parkway CP5 has the same - not clear if this makes it by May 2017. To Bristol Temple Meads, at least via Chippenham, CP5 has May 2017, now December 2018. To Cardiff, CP5 is December 2017, now December 2018. To Swansea, CP5 has May 2018, now December 2018 (but ...). Branch lines, CP5 has Dec 2017, now no fixed date. Basingstoke, CP5 had TBA, and that is now TBA but later than before.
I was told that the first EMUs▸ will run Paddingtom - West Drayton, replacing the Greenford trains which will convert to shuttles from West Ealing. This will allow driver familiarisation etc. in advance of the main start. DfT have this step in May 2017, which must be wrong - it's mentioned under SLC1, which ends on that date - but I can't remember how much earlier the correct date is.
|
|
|
Logged
|
|
|
|
TaplowGreen
|
|
« Reply #1144 on: March 24, 2015, 19:21:52 » |
|
Interestingly FGW▸ Twitter feed today was stating electrification of "London to Bristol, Oxford and Newbury will be complete by 2016.South Wales 2017" .....hmmmmmm
|
|
|
Logged
|
|
|
|
IndustryInsider
|
|
« Reply #1145 on: March 24, 2015, 19:45:37 » |
|
I was told that the first EMUs▸ will run Paddingtom - West Drayton, replacing the Greenford trains which will convert to shuttles from West Ealing. This will allow driver familiarisation etc. in advance of the main start. DfT» have this step in May 2017, which must be wrong - it's mentioned under SLC1, which ends on that date - but I can't remember how much earlier the correct date is.
December 2016 for the Greenford shuttles I think. Though I thought it was Paddington to Hayes, rather than West Drayton? The former already being wired of course.
|
|
|
Logged
|
To view my GWML▸ Electrification cab video 'before and after' video comparison, as well as other videos of the new layout at Reading and 'before and after' comparisons of the Cotswold Line Redoubling scheme, see: http://www.dailymotion.com/user/IndustryInsider/
|
|
|
stuving
|
|
« Reply #1146 on: March 24, 2015, 20:08:14 » |
|
December 2016 for the Greenford shuttles I think. Though I thought it was Paddington to Hayes, rather than West Drayton? The former already being wired of course.
Since June 2016 was the original date to finish the wires to Oxford, Newbury etc. you imagine Network Rail would be very keen to at least finish and hand over something by then (for 1st train in December). Though this bit is actually being done by Crossrail. Presumably this date has been negotiated into their contracts? Maybe NR» are more confident of Crossrail's ability to meet milestones than their own.
|
|
|
Logged
|
|
|
|
Electric train
|
|
« Reply #1147 on: March 24, 2015, 21:58:22 » |
|
I was told that the first EMUs▸ will run Paddingtom - West Drayton, replacing the Greenford trains which will convert to shuttles from West Ealing. This will allow driver familiarisation etc. in advance of the main start. DfT» have this step in May 2017, which must be wrong - it's mentioned under SLC1, which ends on that date - but I can't remember how much earlier the correct date is.
December 2016 for the Greenford shuttles I think. Though I thought it was Paddington to Hayes, rather than West Drayton? The former already being wired of course.
All this goes to explain all the phone calls from the Crossrail team asking if I was interested in position in their Electrification team, quite a bit to do was one of the things said to me
|
|
|
Logged
|
Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
|
|
|
stuving
|
|
« Reply #1148 on: March 24, 2015, 23:05:21 » |
|
December 2016 for the Greenford shuttles I think. Though I thought it was Paddington to Hayes, rather than West Drayton? The former already being wired of course.
All this goes to explain all the phone calls from the Crossrail team asking if I was interested in position in their Electrification team, quite a bit to do was one of the things said to me According to Crossrail, Western end electrification is due to complete 21062016 (as is West Drayton but not Hayes & Harlington stations). But it's being managed by Network Rail anyway, so the difference from GW▸ electrification is NR» working for Crossrail with TfL» 's money (but handing over to themselves for non-Crossrail use first) rather than working for themselves. I found Balfour Beatty's announcement they were doing the OHLE and AT stations for Stockley Park - Maidenhead, with completion in 2016 (OHLE) and 2017 (AT). Which doesn't quite square. Who's doing the power infeeds I don't know. Since these contracts were let in October 2013 and June 2014, there was "quite a bit to do" right from the start. ( So, do you trust Crossrail/NR to do better than me at getting all the bits in the right order?)
|
|
« Last Edit: March 25, 2015, 18:23:31 by stuving »
|
Logged
|
|
|
|
ChrisB
|
|
« Reply #1149 on: March 25, 2015, 09:40:47 » |
|
According to Crossrail, Western end electrification is due to complete 2106 (as is West Drayton but not Hayes & Harlington stations).
In this case, I hope Crossrail (and you!) are very wrong.... :-)
|
|
|
Logged
|
|
|
|
Electric train
|
|
« Reply #1150 on: March 25, 2015, 18:19:01 » |
|
December 2016 for the Greenford shuttles I think. Though I thought it was Paddington to Hayes, rather than West Drayton? The former already being wired of course.
All this goes to explain all the phone calls from the Crossrail team asking if I was interested in position in their Electrification team, quite a bit to do was one of the things said to me According to Crossrail, Western end electrification is due to complete 2106 (as is West Drayton but not Hayes & Harlington stations). But it's being managed by Network Rail anyway, so the difference from GW▸ electrification is NR» working for Crossrail with TfL» 's money (but handing over to themselves for non-Crossrail use first) rather than working for themselves. I found Balfour Beatty's announcement they were doing the OHLE and AT stations for Stockley Park - Maidenhead, with completion in 2016 (OHLE) and 2017 (AT). Which doesn't quite square. Who's doing the power infeeds I don't know. Since these contracts were let in October 2013 and June 2014, there was "quite a bit to do" right from the start. NR are doing all the "on network" for Crossrail and will remain the asset owner, operator and maintainer; only the tunnels sections will be owned, operated and maintained by TfL. The in feed for Crossrail is at Kensel Green, the 2 large 400kV transformers are on site ( by the gas holders) the 400 kV grid line is a cable tunnel under the Canal. The next GWEP▸ grid is Didcot. Maidenhead is MPATS▸ so is quite crucial to the whole GWEP until Bramley comes in when Reading Basingstoke is electrified. My particular specialty is Distribution and not the knitting
|
|
|
Logged
|
Starship just experienced what we call a rapid unscheduled disassembly, or a RUD, during ascent,”
|
|
|
BerkshireBugsy
|
|
« Reply #1151 on: March 25, 2015, 21:04:16 » |
|
I am sure this question has been asked about Crossrail before but I didn't know what to search for.
I was travelling home from Paddington in the light for once and I was trying to work out how the crossrail track will run along side the existing 4 tracks in places where there is limited space.
I did find some volumes of maps on the Crossrail web site but there are so many of them
On a separate note I was driving from Pangbourne along the road which runs between the Thames and the GWML▸ and was very impressed with the progress on erecting the OLE▸ gantries but then it was the first time I had been along there in ages.
|
|
|
Logged
|
|
|
|
Adelante_CCT
|
|
« Reply #1152 on: March 25, 2015, 21:30:23 » |
|
I was travelling home from Paddington in the light for once and I was trying to work out how the crossrail track will run along side the existing 4 tracks in places where there is limited space.
From Paddington there are 6 running lines before merging into 4 shortly before Old Oak Common, the crossrail tracks will join up with these 6 tracks and will then run on the 2 relief lines (of the existing 4 tracks that operate west of Old Oak)
|
|
|
Logged
|
|
|
|
paul7575
|
|
« Reply #1153 on: March 25, 2015, 22:53:40 » |
|
I am sure this question has been asked about Crossrail before but I didn't know what to search for.
I was travelling home from Paddington in the light for once and I was trying to work out how the crossrail track will run along side the existing 4 tracks in places where there is limited space.
As in the previous reply, Crossrail's tracks merge with the existing reliefs by Old Oak Common. A diagram was posted quite recently in the Crossrail thread here: http://www.firstgreatwestern.info/coffeeshop/index.php?topic=818.msg172796#msg172796
|
|
|
Logged
|
|
|
|
BerkshireBugsy
|
|
« Reply #1154 on: April 12, 2015, 17:59:03 » |
|
I was very surprised today (Sunday 12th April) when driving over Thatcham level crossing to see that the new footbridge construction had come on leaps and bounds. It's still not in use but in the attached picture you can see the new one in the distance.
This picture was taken standing on the level crossing looking eastbound
|
|
|