Im sure its been explained before.. but when the IEP▸ sets are ordered for the Great Western route, will there be suffucient to replace every single HST▸ ... or will it only be to replace the HSTs whihch First rent, not incluyding the ones they purchased?
I think it is in another thread,but couldn't find it easily, so I'll repeat the numbers from the
ITT▸ , page15 refers:
http://www.dft.gov.uk/pgr/rail/pi/iep/iepinvitationtotender/iepinvitationtotender.pdfThe tender calls for a number of daily diagrams, so you'd expect at least 10% more physical trains, and of course there are full length and half length trains, helpfully they list 'full length equivalents'.
GWML▸ Phase 1
Self power 24 Full
Bi-mode 38 Half (19 Full equivalent)
GWML Phase 2
Self power 15 Full
Bi-mode 3 Half (1.5 Full equivalent)
So that is 80 (59.5 full equivalent) daily diagrams, so probably equates to about 88 (66 full equivalent) trains, which compares favourably with the number of HSTs, I think.
Paul