stuving
|
|
« Reply #13 on: September 28, 2023, 22:57:44 » |
|
There's been some criticism of the control decisions that evening, and I've been trying to get a fuller picture of what they were. If you look at the record on RTT» , the block (at a viaduct south of Lockerbie) started after the trains that ran through Lockerbie at 16:09 (both ways). The first passenger trains to run after that were at 2111 (south) and 2122 (north).
But there were some goods trains in between - south at 2019 (held at its Mossend origin), 2037 (held at Mossend en route), 2040 (held at its Shieldmuir origin); north at 2022 (having been held south of Gretna), 2047 (having been held north of Carlisle). I guess these ran first as they could be held in places between main stations, and restarted at shorter notice than passenger trains. The line block must have actually been lifted by 2000; some reports say it was before 1930.
One bus is shown leaving at 1715, as RRB▸ and timetabled, from Carlisle to Motherwell via Lockerbie. I guess there was some work being done that day, despite it being a Monday.
The next train southbound after the closure was 1M16, which stopped at Lockerbie until a bit before 2000, then returned to Glasgow, though by the time it reached Carstairs the line had reopened. It shows on RTT as cancelled, and on Liverail as "Cancelled At Glasgow Central High Level. Reason IR [Broken/cracked/twisted/buckled/flawed rail] AT ORIGIN", but with some timings en route and last timed as "16:45 Arr. Lockerbie 16 Late". The next (9M59) has a last timing of "16:18 Arr. Carlisle P3 4 Late". I imagine that went back to Glasgow too, though neither northward run is shown.
Northbound, the last train to get through (1S63) left Carlisle at 1553 (so it took 16 minutes to get to Lockerbie). Then there's a gap (apart from the train via Dumfries that left at 1609) until 1618, when a TPE▸ service for Edinburgh was terminated short. That was followed by two AWC: 1S68 (GLC▸ ) at 1652 and 9S70 (EDB) at 1709.
After that, then next train isn't due until 1852: 1S72 (GLC) which was terminated at Preston at 1637, as were 9S77 (GLC) at 1751 and 61L, 1S74 (TPE, LIV-GLC) at 1658, 1S75 (TPE, to EDB) at 1708, 1S78 (GLC) at 1828 (50L), 9S80 (EDB) at 1838 (17L), 1S82 (GLC) at 1855 (17L), and 9S93 (EDB) at 2008 (17L) - the train in the report. There were two more trains terminated that night, 9S97 at Crewe, and 1S98 at Preston at 2221, 41 late. Both (as with other later cancellations) have recorded reason "IS [Track defects (other than rail defects i.e. fish plates, wet beds etc)]".
So two northbound AWC trains were stopped at Carlisle, six at Preston (plus one late at night), and one at Crewe; also three (smaller) TPE ones. One train was cancelled at Euston. That does not seem unreasonable, if the objective is to take trains as far as possible, subject to the capacity of the stations for trains and lost passengers.
Only three trains got through after the line reopened: 9S85 delayed before and at Preston - where is was cancelled on arrival, then uncancelled again - and which it left at 1948 (55L), 1S83 TPE started short from Carlisle at 2018, and 1S90 that was held at Preston and left at 2008 (25L). Those all arrived nearly an hour late, but well before midnight - and the last two trains didn't make it.
Given the size and number of mainline trains, which are electric, and that any diversion has smaller trains, and isn't, it's inevitable that there was a massive problem for Avanti's staff to deal with. With so many trainloads of passengers stuck en route, I don't think they did too badly. But the line reopened by 2000, so in principle most trains that set out should have been able to reach their destinations, even if hours late. Since SNCF▸ , for example, do generally manage to do that, it's fair to ask why - what is the difference? Staffing and employment terms, no doubt, but that if so that's a problem rather than an answer.
Of course the lack of viable diversions and whatever makes staffing such an issue are also the results of earlier decisions, not acts of God.
|