, informing them of my petition (and pointed out the high number of signatures).
Thank you for your email of 8 April 2008, about the redoubling of the
Cotswold Line and drawing our attention to your E-Petition on the Prime
Minister's website.
Below is some background information which may be of interest to you:
Network Rail is, and has been for some time, considering the partial or
total redoubling of the Cotswold Line. This is based on (a) improving
service performance, since the presence of single line results in delays
in one direction being transmitted into delays in the service in the
opposite direction (this can react throughout the day), and (b) creating
greater flexibility for future timetables. As you will be aware, this
is a busy line in terms of usage of available track capacity, and
recovery from delays is difficult.
However, Network Rail has to identify and make a business case for any
scheme that it wishes to deliver. Only if the necessary results could
be achieved would the scheme be progressed. At present, a team is
investigating the various options and checking the practicability and
likely cost of each of them.
Network Rail's business plan shows that a decision on the preferred
option and whether there is a business case should result from this
around June or July 2009 (which gives some indication of the amount of
work that is required to reach that stage). The Route Plan suggests
completion in December 2010.
Much of the business case would be based on the amount of delay (and
payments made by Network Rail to train operating companies (
TOCs▸ ) as a
result of it) that would be saved. Other industry benefits can also be
taken into account and it is open to other beneficiaries - Councils,
etc. - to contribute if non-industry benefits enable them so to do.
Potential increases in housing (and, therefore, traffic), reductions in
CO2 emissions, reduced congestion, etc., can all be taken into account.
Clearly, there would be a huge amount of work to be done on the ground,
clearing and bringing back into usable condition the vacant formation,
track relaying, changes to pointwork, construction of new platforms
where the old ones have been demolished (together with associated
Disability Discrimination Act works that would legally have to be
undertaken if a station was being improved), and complete resignalling
of the route. It remains to be seen how much, if anything, can be
afforded. It should be noted that, because of changing standards, it
might not be possible to redouble the whole line if bridges or, in
particular, the two tunnels do not provide sufficient clearance for two
trains to pass safely.
You can find more information by visiting
www.networkrail.co.uk and
searching for Cotswold Line.
I hope this is useful.
Yours sincerely,
Bill Dennis
Customer Correspondence Team
Not good. Was not impressed.
At one point it was as if they did not want disabled people to hav access to stations.
And what is that cr*p about 2 trains might not be able to pass under bridges/tunnels - don't they realise that the line was double originally?!