I went looking for the
Western Route Strategic Plan (of March 2019) to see what it said about Network rail's thinking in the context of
WECA» . But, while its content is diffuse and hard to summarise, it does relate to the whole route and has never had a mention of its own. So here it is, for future refernce.
Unlike the Wessex Route version, it doesn't give a timetable of major possessions. It has comments about all areas of infrastructure work, except - it appears - enhancements. I think that's because these arise from the "pipeline" rather than from the Route itself, but I may be wrong. Under a picture of said pipeline, it says (P 61, FID is final investment decision):
The route has 3 DfT» funded Enhancements that have currently passed FID (November 2018), these are Bristol Temple Meads Station Capacity, Western Route Flood Resilience and Great Western Electrification (committed elements).So when it says under "delivery strategy" (P 63):
There are no OLE▸ critical resources required in CP6▸ as only renewals campaign changes remain for the Great Western Electrificationmy guess is that the "Hendy tail" is parked on a shelf at
NR» Towers and isn't part of the route's plans until taken off and fed into the dust-blower. (Or maybe the shredder, of course.)