There was a concentrated effort to complete as much of the tank works as possible before the Christmas break. Backfilling around the structure was completed before the shutdown, manholes installed and a first layer of protection laid on top of it (see photo below). Further basecourse surfacing and car parking plots were laid in the south car park.
Image showing the first layer of protection laid
There were no traffic or safety incidents reported during the Christmas and New Year site closure.
November 2018
November has seen a lot of work done on the drainage system for the north car park and adjoining area. The tank to manage the outflow of water has almost been completed. Despite the inclement weather, sheet piles have been installed (see below, top left photo), the ground excavated and a reinforced concrete base laid (right), and almost all of the pre-cast tank units installed (bottom left). The final few units will be installed in early December.
There has also been continued work on other areas around the north car park, the south car park and to entrances and footways along the A30.
A30 Completion delayed - Following extensive challenge and discussion it has been agreed between Cornwall Council, Highways England and Wills Brothers that it would not be safe to commission the new A30 signals until the permanent car park entrance has been constructed. This has the impact of postponing the completion of A30 works until 3 March 2019. The Council instructed changes to the drainage (including the large tank) which will be beneath the access road leading to the level crossing and north car park entrance. The current temporary car park entrance would exit within the signalised junction area, adjacent the station access, and is not considered to be safe to operate in that situation as it could cause traffic to queue back onto the A30.
All site works are expected to be completed in the first week of April 2019 with the south car park opening, after safety audit and handover to
GWR▸ , to operate from mid May 2019 to coincide with the new two trains per hour main line train service and the completed St Ives Bay platform works.