Sorry if the undermentioned has previously been posted on this forum and I have missed it.
I have copy and pasted the text of a briefing note that was forwarded to me from my local town council, Yate Town Council, which is also covers the complete closure of Bristol Parkway for two weeks in September.
Network Rail Infrastructure Limited Registered Office: Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN
Registered in England and Wales No. 2904587
www.networkrail.co.ukWednesday 14 June 2017
Briefing Note: Railway Upgrade Plan: Working in Wiltshire and
South Gloucestershire – 19 August to15 September 2017
What does the work involve?
We’ll be working day and night from 19 August to 15 September along the railway from the
outskirts of Royal Wootton Bassett, Wiltshire, to Patchway/Filton junctions, South
Gloucestershire.
As part of the Greater West Programme, we are electrifying the line to bring passengers
quieter, more frequent and more reliable services between London Paddington and Cardiff.
Over the entire four weeks, we’ll be working from the outskirts of Royal Wootton Bassett,
through Brinkworth, Little Somerford, Rodbourne, Hullavington, Acton Turville, Old Sodbury,
Chipping Sodbury and Yate to Westerleigh Junction.
From 2 September to 15 September 2017, our work area will extend to include Westerleigh
Junction towards Yate station, Coalpit Heath, Winterbourne, Stoke Gifford and Bristol
Parkway station, up to Patchway/Filton junctions.
The work includes:
Carrying out the piling required to install the foundations which will support the
electrification equipment.
Installing the equipment, including trackside masts and overhead wires at some
locations.
Installing electrification equipment in Chipping Sodbury and Alderton tunnels.
Improving flood resilience at Chipping Sodbury sidings.
Preparing Bristol Parkway station for the arrival of new InterCity Express trains,
including the construction of a fourth platform.
What can our lineside neighbours expect?
Unfortunately, some of the construction work will be noisy and we would like to thank our
neighbours in advance for bearing with us. As well as the activity on the railway, there will be
deliveries of plant and materials by road to our road-rail access points and compounds along
the route.
Network Rail Infrastructure Limited Registered Office: Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN
Registered in England and Wales No. 2904587
www.networkrail.co.ukHow will we manage the impact on our neighbours?
We recognise that our work can be disruptive to those living or working nearby but please be
assured that every effort is made to minimise any unnecessary noise and we have reminded
all staff and contractors to be considerate of the environment they are working in.
Will my train journey be affected?
Over the four weeks, trains will still be running using diversionary routes. Rail replacement
bus and coach services will be in place for some journeys. Bristol Parkway station will be
closed from 2 September to 15 September. Please plan ahead at
gwr.com/bristolparkway2017 or crosscountrytrains.co.uk
Please also note that South Gloucestershire Council is starting work in July 2017 for a period
of up to 52 weeks on the essential repair works to the Bromley Heath Viaduct, located on the
A4174 ring road. The ring road over the viaduct will be reduced to one lane in each
direction.
GWR▸ has added extra time into its bus schedule in case of related traffic
congestion. For more information please visit
www.southglos.gov.uk/bhviaduct.
How can I find out more?
Visit our dedicated webpage at
www.networkrail.co.uk/westernupgrade which will be
available from Monday 19 June. It contains more detailed information about the work we will
be carrying out and will be updated regularly as the project progresses.
Or join us at one of our drop-in sessions, when members of the project team will be on
hand to explain the work and answer your questions:
Thursday 22 June, Brinkworth Village Hall, 4pm to 6pm
Tuesday 27 June, Little Somerford Village Hall, 4.30pm to 7pm
Thursday 29 June, Coalpit Heath Village Hall, 4.30pm to 7pm
Tuesday 4 July, Ridgewood Community Centre, Yate, 4.30pm to 7pm
Tuesday 11 July, The Old School Rooms, St Michael’s Centre, Stoke Gifford,
4.30pm to 7pm
Wednesday 12 July, Chipping Sodbury Town Hall, 4.30pm to 7pm
Thursday 13 July, Trinity Primary School, Acton Turville, 6pm to 8pm
Tuesday 18 July, Old Sodbury Village Hall, 4.30pm to 7pm
Wednesday 19 July, Hullavington Village Hall, 5.30pm to 8pm
Tuesday 25 July, All Saints Church Hall, Winterbourne Down, 4.30pm to 7pm.
Any questions?
If you have any queries about our work, please email us at
crwest@networkrail.co.uk or call
our 24-hour National Helpline on 03457 11 41 41. For updates, follow us on Twitter
@networkrailwest