NickB
|
|
« on: January 25, 2016, 09:01:31 » |
|
Morning,
I noticed a 'small print' note on the tube map this morning saying that the Bakerloo line will not be stopping at Paddington from April 2nd until August.
Can anyone confirm this, or know what is being done? I guess its still early days but the publicity isn't good. That's going to royally shaft my commute. They did this for a couple of weeks in 2014(?) and the results were not good - 4 months is a nightmare.
|
|
|
Logged
|
|
|
|
|
didcotdean
|
|
« Reply #2 on: January 25, 2016, 09:12:47 » |
|
Closure relates to construction of the interconnection with the Crossrail platforms.
|
|
|
Logged
|
|
|
|
stuving
|
|
« Reply #3 on: January 25, 2016, 10:40:43 » |
|
It's a bit of an afterthought, not part of the Crossrail project but a separate "Paddington Bakerloo Line Link Project". Its a substantial bit of work, and let by London Underground to a Costain/Skanska JV. More words and pretty pictures here and here.
|
|
|
Logged
|
|
|
|
NickB
|
|
« Reply #4 on: January 25, 2016, 10:54:13 » |
|
Interesting - thanks all.
|
|
|
Logged
|
|
|
|
ChrisB
|
|
« Reply #5 on: January 25, 2016, 11:17:06 » |
|
No afterthought at all.
Was part of the plans shown to Customer Panels way back before Eastbourne Terrace was dug for the Crossrail platforms. The connection was shown then as going under the lawn, and we were informed that the Bakerloo stations were to shut for a period.
However, no sign of any mitigation yet, which IMO▸ , needs the eastbound circle line to continue beyond Edgware Road to at least Moorgate. That would at least partially split the likely overcrowding of the eastbound H&C platform which isn't exactly very wide
|
|
|
Logged
|
|
|
|
stuving
|
|
« Reply #6 on: January 25, 2016, 12:06:31 » |
|
No afterthought at all.
Was part of the plans shown to Customer Panels way back before Eastbourne Terrace was dug for the Crossrail platforms. The connection was shown then as going under the lawn, and we were informed that the Bakerloo stations were to shut for a period.
The original plan was dropped due to fears the Brunel train shed might fall down ( from the inspector's report on the TWA application, dated December 2013): 3.11 This Order is required because it is not possible due to engineering constraints to deliver the link within the limits of deviation contemplated in the 2008 Act. The 2008 Act scheme or the reference scheme was based on a shallow tunnel. This scheme had to be discounted due to the predictions of ground loss and significant settlement impact on the Grade 1 listed Brunel Train Shed and disruption of Network Rail operations and passenger flows on the concourse , and critically due to the residual risk of the collapse of the tunnel face and consequential risk to construction workers and the travelling public. 3.12 The preferred deep tunnel scheme was arrived at following a process of Value Engineering . Its preferential features , and the need to seek powers through the Order because the deep tunnel fell outside the limits of deviation of the 2008 Act, are set out in Mr Judd^s evidence .
So this new hole is, in that sense, an afterthought; with its own TWA order in February 2014. How much disruption the original plan would have caused is hard to say. Interestingly, other than the quoted comment about passengers in the main line station, the TWA inspector didn't include that kind of passenger disruption in his consideration of things that need mitigating.
|
|
|
Logged
|
|
|
|
paul7575
|
|
« Reply #7 on: January 25, 2016, 12:08:53 » |
|
However, no sign of any mitigation yet, which IMO▸ , needs the eastbound circle line to continue beyond Edgware Road to at least Moorgate.
Highly unlikely if not impossible, there are no paths for that to be done without cancelling the normal through trains off the Met beyond Baker St. Paul
|
|
|
Logged
|
|
|
|
TaplowGreen
|
|
« Reply #8 on: January 25, 2016, 12:11:49 » |
|
This will be absolutely horrendous for all those (myself included) who use the Bakerloo line from Paddington, there is no way that the already overcrowded H & C/Circle lines will be able to cope with the extra traffic on a daily basis.
Looks like they've had almost 2 years to plan, so what mitigation is going to be put in place for passengers? (or as stuving has suggested, maybe they haven't factored this in?
Anyone who has ever tried to get on the H & C/Circle when the Bakerloo has fallen over will know exactly what I mean - 6 months of this does not bear thinking about!
|
|
|
Logged
|
|
|
|
ChrisB
|
|
« Reply #9 on: January 25, 2016, 12:18:54 » |
|
April to August = 6 months?
|
|
|
Logged
|
|
|
|
TaplowGreen
|
|
« Reply #10 on: January 25, 2016, 12:27:29 » |
|
April to August = 6 months?
Sorry - I was using a faulty Network Rail abacus left over from their electrification project. OK then 4 and a bit months - the more important question remains - what are the plans to mitigate the horrendous overcrowding which will be a by product of this closure?
|
|
|
Logged
|
|
|
|
ChrisB
|
|
« Reply #11 on: January 25, 2016, 12:33:20 » |
|
However, no sign of any mitigation yet, which IMO▸ , needs the eastbound circle line to continue beyond Edgware Road to at least Moorgate. Highly unlikely if not impossible, there are no paths for that to be done without cancelling the normal through trains off the Met beyond Baker St. Off-peak they certainly could. Maybe to Baker Street plats 5&6 then, reversing there? Most Bakerloo pax would be changing there onto that line anyway....
|
|
|
Logged
|
|
|
|
Thatcham Crossing
|
|
« Reply #12 on: January 25, 2016, 13:36:30 » |
|
TG hasn't said where he's travelling to (by Tube from PAD» ), but the 6-7 minute walk to the Central Line at Lancaster Gate is a good way to avoid the Circle/H&C if going east (as I often am) to the likes of the City (Bank/St Pauls) or Canary Wharf (Bank, then DLR▸ )?
I often find the Circle/H&C really slow, as Edgware Road and Baker Street seem to be bottlenecks, due to junctions with other lines.
|
|
|
Logged
|
|
|
|
Ollie
|
|
« Reply #13 on: January 25, 2016, 14:03:43 » |
|
Appreciate the replies listed here...Bakerloo Line got back to me on Twitter a few moments ago advising it's the Crossrail work but they're also doing some escalator refurbishment work too.
|
|
|
Logged
|
|
|
|
NickB
|
|
« Reply #14 on: January 25, 2016, 14:22:36 » |
|
Appreciate the replies listed here...Bakerloo Line got back to me on Twitter a few moments ago advising it's the Crossrail work but they're also doing some escalator refurbishment work too.
Thanks ollie - did they say what arrangements they are going to make to help passengers make their onward journeys?
|
|
|
Logged
|
|
|
|
|