CP5▸ Enhancements Delivery Plan (link loads PDF) now contains, and so confirms, the timescale for 10-car trains to run to Reading (and Ash Vale).
Activities and milestones Milestone | Description | Date | Status |
GRIP▸ 3 completion | Single option selection | June 2015 | Regulated Output |
GRIP 4 completion | Single option scope defined | September 2015 | Indicative |
GRIP 6 start | Start on site | April 2016 | Indicative |
GRIP 6 completion | Infrastructure ready for use | May 2017 | Indicative |
What it does not say is how many platforms are to be lengthened to 204 m (or longer), and how many left for
SDO▸ to cope with. All it has is this rather ambiguous statement:
The project includes a review of options to allow 10 car services to stop at Feltham, Egham and Chertsey.
Just a minute - there's another bit further down - but no, that only covers the
ASDO▸ infrastructure and platform works to Windsor and Weybridge via Virginia Water, and on the LSW Main Lines. These are already well past GRIP 3, so presumably deciding what gets done to which station only gets done during GRIP 3.