Broken down engineering train at some point meant late hand back
I presume the T3 was taken at Liskeard to close the line south of there so the broken down engineering train may well have been this one which passed Liskeard just shy of 4¾hrs late and got later and later on its journey to Westbury Down
TC▸ where it arrived 6hrs 55mins late:
https://www.realtimetrains.co.uk/service/gb-nr:U36905/2021-11-13/detailedThis in turn meant that 1C50 (Night Riviera, 2345 Paddington to Penzance) arrived Plymouth on-time at 0511 but sat there for nearly 4 hours before continuing.
https://www.realtimetrains.co.uk/service/gb-nr:G59202/2021-11-12/detailedSeems to have caused quite a few hefty delays does that engineering train.
Dave