In Bristol, this could be another chance to trot out the now mythical Portway Park and Ride station, scheduled for opening in Autumn 2013 IIRC▸ . Although the only way that is shovel ready would be in the cemetery context of the term by now.
That's probably at
GRIP▸ 4 or 5 isn't it?
If it is, it is being kept well under wraps. The last mention of it in the
Bristol Post is from August 2014, suggesting an opening date of April 2016. The papers for the Joint Transport Board meeting on 12 September 2014 say:
Portway Park & Ride platform
19. It was hoped that the second Network Rail Value Management Workshop for the project would be held in September 2014. Unfortunately due to Network Rail’s current busy programme of works, including electrification and Filton Bank four tracking, this workshop has been delayed until early 2015. Network Rail is currently procuring consultants for GRIP 3 project development. Sufficient time has been built into the programme to achieve a Summer 2016 opening date, depending on the costs that emerge through the project’s development.
March 2015's papers show (December 2014's said similar):
29. The current GRIP Stage 2 study is nearing completion and a review meeting has been arranged for mid-March 2015 where Network Rail and their consultants ARUP will present the findings of the study. It is anticipated that the key issues will be around signalling requirements for the West Town Gate level crossing to minimize the downtime of barriers (which is also required for MetroWest Phase). It is anticipated that the GRIP Stage 2 report will be published in April 2015.
July 2015 sees a rather upbeat report:
17. The GRIP Stage 2 study has been completed and we expect Network Rail to issue the report to Bristol City Council later this month. The emerging findings of the study indicate that there are feasible options to deliver a new platform to serve the Park & Ride site with some rail signal mitigation works required. Bristol City Council will consider these options in the context of their likely cost and implications for the business case, and the potential delivery timescales.
October 2015's report is concise:
Portway Park & Ride platform
15. Bristol City Council is awaiting the final GRIP Stage 2 study.
Come the end of January 2016, the papers begin to assume a pattern familiar to Bristol transport watchers:
28. The GRIP Stage 2 report has been completed by Network Rail. Bristol City Council has identified £0.35m funding to take the project forward to GRIP Stage 3 with associated work streams in 2015/16 and for two years afterwards. A bid may be made to the Department for Transport’s New Stations Fund, details of the new round of funding still to be announced, but the project is not reliant on a bid. Delivery is planned for the first half of 2019.
No explanation for the 3-year slippage. So it is that in the papers for the meetings in March and June 2016, we read:
(Intentionally left blank)
This suggests it has made it to GRIP 2. I have heard comments elsewhere that suggest the down time of the level crossing at West Town Road may well be fatal to the project.