The GWR▸ main line electrification plans had 9 car electric trains being delivered first, with 5 car bimodes to follow. But electrification was / is late and has been curtailed in the current term to Thingley and Cardiff, meaning that 9 car electric trains wouldn't be able to operate on the main routes planned for them - London to Bristol Temple Meads and London to Swansea. So the order for 9 car trains was changed to add in diesel engines / make them bimodes too - and by the time that was done, contracts arranged, designes changed, other bits ordrered, they had missed their place on the production lines and the 5 car bi-modes were built (and delivered) first.
Not true! (I'm sure I've said this before, too.)
The 2015 franchise agreement (dated 22/3/15) included from p 138 "delivery dates", meaning the date an extra unit would be in the depot, and another date when each extra one would be available to GWR, and these were copied from the
MARA▸ p 307 (revised 31/1/14).
5-car bimodes:
type acceptance 2/2/17
delivery train 1 25/5/17
first trains (2 off) for GWR 8/6/17
32 (all) trains for GWR 18/1/18
delivery train 36 8/2/18
9-car electrics:
type acceptance 20/10/17*
delivery train 1 15/2/18
first trains (2 off) for GWR 1/3/18
10 (all) trains for GWR 26/4/18
delivery train 12 3/5/18
*now corrected