Show Posts
|
Pages: [1] 2 3
|
1
|
Journey by Journey / Swindon to Gloucester / Cheltenham / Re: Swindon to Kemble re-doubling - ongoing discussion and updates
|
on: November 12, 2014, 14:42:02
|
bobm, have you heard of any planning for a possible local train service that would stop in places such as Minety or perhaps Chalford in future? Or alternatively, have you heard anything indicating that the double-tracking will have no effect on adding stations and local stops? I often think back to the days when the Auto-train used to run between Chalford and Gloucester, with maybe 10 halts in-between. A different Britain! How I cherish memories of those days!
|
|
|
3
|
Journey by Journey / Swindon to Gloucester / Cheltenham / Re: Swindon to Kemble re-doubling - ongoing discussion and updates
|
on: September 20, 2014, 15:47:49
|
I worked at Gloucester on the S & T for 43 years and can confirm that the line was singled in the summer of 1968. I worked there on the weekend the work took place. There was no thought of mothballing it for a period of time in case of a re-think, just rip it out and centralise the single track for ease of maintenance (to save money).
Glawster, you mentioned that you were working 'on the weekend in the summer of 1968' when the line was singled. Probably took more than just one weekend to remove the second track and slew the remaining one, but probably didn't take much more than a few weeks. It says it all about our modern times when it takes (including planning and preparatory work) more than a year and 45million pounds to relay the second track from Swindon to Kemble. Same thoughts as I have on the costs for extending the Jubilee Line versus the costs (in 1900 pounds) and simplicity/functionality involved in building of the Central Line. One might say that endless safety considerations and workers no longer working for peanuts makes up the difference, but I think there's more to it than that. Just too much red tape and Government involvement in every aspect of our lives these days.
|
|
|
6
|
Journey by Journey / Swindon to Gloucester / Cheltenham / Re: Swindon to Kemble re-doubling - ongoing discussion and updates
|
on: August 20, 2014, 23:40:57
|
Has anyone heard anything further on how control of the new Swindon-Kemble double track is to be handled until the new Didcot control centre fully takes over from the Swindon panel? I seem to remember someone mentioning that Didcot would have control of the double track from its opening later this month, even though the Swindon panel would still be in use until later this year.
Please Refer to Post #345 on this thread. Thanks, Phile. Based on control over all in/out rail traffic at Swindon having to be at one location and based on Swindon-Kemble double track being operated from Didcot from the end of this month it must follow that Swindon Panel will no longer be in use from that time. Some earlier posts indicated that transfer of control to Didcot was behind schedule and wouldn't take place until late in 2014, but I guess that's not the case.
|
|
|
8
|
Journey by Journey / Swindon to Gloucester / Cheltenham / Re: Swindon to Kemble re-doubling - ongoing discussion and updates
|
on: July 20, 2014, 01:53:09
|
"New signal equipment has also been installed."
It hasn't yet, has it? Or at least it's still in progress. There was, however, a minorly momentous occasion last week where I saw two trains pass each other on the line for the first time (a NR» test train on the down and a scheduled service on the up).
Two trains passing each other. Does this mean that the ends of the new track have now been connected to the existing track at both ends, with the switches at both ends (including the one at the north end of Kemble Tunnel) no longer being in use?
|
|
|
9
|
Journey by Journey / Swindon to Gloucester / Cheltenham / Re: Swindon to Kemble re-doubling - ongoing discussion and updates
|
on: June 20, 2014, 05:07:29
|
According to the latest update issued by the Swindon Panel Preservation Society, the signalling control of the re-doubled line will be installed at the Thames Valley Signalling Centre in Didcot rather than from a temporary unit at Swindon. bob, does this mean that Swindon will still be in control of the other lines into Swindon but Didcot will be in control of the Kemble segment? If so, how would control be co-ordinated? Doesn't it require the same person(s) in one location being in control of all traffic in/out of Swindon? Just wondering.
|
|
|
10
|
Journey by Journey / Swindon to Gloucester / Cheltenham / Re: Swindon to Kemble re-doubling - ongoing discussion and updates
|
on: June 09, 2014, 16:24:12
|
Ellendune, apparently Network Rail or one of its contractors is setting up a temporary control system at Swindon that will run alongside the Swindon Control Panel so that the Swindon-Kemble double track will come into full operation at the end of August, i.e. no need to wait for regional control to be moved from Swindon to Didcot. The contractors need to have all of the double track in place by 13 July to avoid heavy overrun penalties. By that date all of the new track should be in place apart from the connections to be made at both ends when the existing pair of switches are removed. Their removal and connection of the double track will take place in the same closure period (end of August) as double-track control starts.
|
|
|
13
|
Journey by Journey / Swindon to Gloucester / Cheltenham / Re: Swindon to Kemble re-doubling - ongoing discussion and updates
|
on: April 21, 2014, 14:04:25
|
Does anyone know if the speed limit on the Swindon-Kemble section will change once the redoubling is finished? A while ago one of the coaches on FGW▸ trains had screens on the back of seats and software that allowed you to track the speed of the train. On the Swindon-Kemble section I noticed the speed hitting 120mph. Just wondering if any existing speed limit on the single track will decrease once trains are running on two tracks.
|
|
|
|