Title: Severe Delays at Swindon 18th December
Post by: ellendune on December 18, 2011, 13:42:36
My daughter caught the 10:15 from Cardiff to Swindon today which was stopped outside Swindon for over 1 hour 30 minutes before being able to move into the platforms.  Even with the the problems why was a train left standing just outside a station for such a long time? There was no information as to the likely extent of the delays.



Title: Re: Severe Delays at Swindon 18th December
Post by: dog box on December 18, 2011, 15:56:46
prehaps because there was no where else for it to go, Engineering works at South Marston  on the down main meant that platform 4 was closed meaning that only platfrom 1 and 3 were avalible .
Due to the Engineering works all services were using the bi directional up main, a track circuit failure at approx 930 , meant that pilotman working was introduced which resulted in a huge backlog of trains at each side of the problem


Title: Re: Severe Delays at Swindon 18th December
Post by: ellendune on December 18, 2011, 17:34:28
If there was already single track working then that makes more sense.  Also if effectively the blockage was that close then there would have been nowhere to stack trains east of the Station either. 



This page is printed from the "Coffee Shop" forum at http://gwr.passenger.chat which is provided by a customer of Great Western Railway. Views expressed are those of the individual posters concerned. Visit www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site if you feel that content provided contravenes our posting rules ( see http://railcustomer.info/1761 ). The forum is hosted by Well House Consultants - http://www.wellho.net