All across the Great Western territory => Across the West => Topic started by: lbraine on January 04, 2025, 17:35:46



Title: Old Oak Common Christmas Work
Post by: lbraine on January 04, 2025, 17:35:46
Does anyone know if the planned work at OOC over the Christmas shutdown was completed?

I ask because prior to the shutdown I thought I had read that the work being undertaken was to slew lines (and presumably related infrastructure) into new positions for what will become the new OOC station.

But I’ve just seen a YouTube video post New Year and the line look like they are in the same place.

So did events unfold that meant the planned work could not be completed ? Or am I mis-remembering what was actually going to occur?

I’m left wondering what was actually undertaken during the extended shutdown?


Title: Re: Old Oak Common Christmas Work
Post by: stuving on January 04, 2025, 22:13:23
The first major blockade for moving the existing railway sideways is next year. It will be longer than this year's three days. I think this year was preparatory work by NR, such as moving cabinets and other equipment out of the way of the HS2 construction teams. They will then start building the northern part of the station on land that does not have any operational railway on it.


Title: Re: Old Oak Common Christmas Work
Post by: Electric train on January 05, 2025, 17:03:29
There is also a replacement bridge sections to go in over Old Oak Common Lane and Central Line which will is likely to be phases



This page is printed from the "Coffee Shop" forum at http://gwr.passenger.chat which is provided by a customer of Great Western Railway. Views expressed are those of the individual posters concerned. Visit www.gwr.com for the official Great Western Railway website. Please contact the administrators of this site if you feel that content provided contravenes our posting rules ( see http://railcustomer.info/1761 ). The forum is hosted by Well House Consultants - http://www.wellho.net