New consultation launched on whether to reopen Portishead train lineA new consultation on whether to reopen the train line between Portishead and Bristol Temple Meads has been launched.
Spoken about for years, but first considered as a serious possibility in 2008 – the MetroWest project has rumbled on for almost a decade with seemingly little progress made.
The latest consultation – which will open on Monday, October 23 – seeks to gauge a reaction to the prospect of having an hourly train service between Portishead and Bristol Temple Meads, rather than the half-hourly service initially proposed.
It comes after an updated budget in March revealed the first phase of the project had trebled in cost from £58million to between £145 and £175million.
Transport Secretary, Chris Grayling, has previously promised the line will reopen and the West of England Combined Authority – which includes Bristol, South Gloucestershire and Bath & North East Somerset (B&NES) – Metro Mayor, Tim Bowles has made positive noises about the scheme.
While there is widespread support for the project, it is still unclear where the extra funding will come from, leading many to question whether the line will ever reopen.
The financial uncertainties have slowed down on works on the line - which was originally set to start operating in 2019 – and it now appears that works on the track will not properly begin until 2020 at the earliest.
Portishead is one of the fastest growing towns in the South West and its population has risen by more than 3,000 since 2001 and is expected to increase by a further 8,000 in the coming decade.
The A369 and M5 roads – the main commuter routes in to Bristol – are regularly congested during peak times, and when one or both are blocked it makes it almost impossible for people to drive to and from the city.
TravelWest – the umbrella organisation for Bristol City Council, South Gloucestershire Council, North Somerset Council and B&NES – estimate that the reopened line will provide a £264million boost to the local economy over the next decade.
The consultation document states: “MetroWest Phase 1 will reduce journey times which will not erode over time.
“MetroWest Phase 1 will also increase the number of people living within 30 minutes’ travel time of key employment areas such as the Temple Quarter Enterprise Zone and the sub-region’s Enterprise Areas.
“This will generate a series of wider economic benefits, such as helping to increase business confidence and assisting in job creation.”
The Portishead line was closed to passengers in 1964 under the Beeching cuts. Some 9km of the track is still used for freight services and only “minor works” are required to enable passenger services to run.
However 5km of the track – which are not currently in use – will need greater investment to make it operational.
Two new stations at Portishead and Pill are proposed under MetroWest phase one plans, and train services will also serve Parson Street, Bedminster, and Bristol Temple Meads stations.
If successfully reopened, the branch line will be owned and maintained by Network Rail and the train service will be operated by the local train operator which is currently Great Western Railway.
Alongside the Portishead line, phase one of the MetroWest project includes running half-hourly trains on the Severn Beach Line and to Keynsham and Bath Spa.
Phase two of the project will see the Henbury Spur route reopen and improvements made to the Yate corridor.
Once the consultation has concluded on Monday, December 4, a final plan will be drawn up for the Metro West scheme. If additional funding for the scheme is secured, the plan will then be submitted to central government in the spring.
It will take around 18 months for the plan to be assessed and formally approved or rejected by government. If approved works could begin in early 2020.
Information about the consolationThe consultation will open on Monday, October 23 and close on December 4.
Consultation documents and questionnaires are available on the TravelWest website or can be requested by calling 0117 922 4513.
A number of public exhibitions on the scheme will take place on the following days:
Friday, November 10 – Between 12.30pm and 7.30pm at Somerset Hall, The Precinct, Portishead,
Wednesday, November 15 – Between 12.30pm and 7.30pm at the Engine Shed, Station Approach, Bristol, BS1 6QH
Tuesday, November 21 – Between 1.30pm and 7.30pm at Trinity Anglican Primary School (Community Hall), Marjoram Way, Portishead, BS20 7JF
Wednesday, November 22 – Between 12.30pm and 7.30pm at Ashton Gate Stadium, Ashton Rd, Bristol, BS3 2EJ
Thursday, November 23 – Between 3.30pm and 7.30pm at Long Ashton Community Centre, Keedwell Hill, Long Ashton, BS41 9DP
Friday, November 24 – Between 12.30pm and 7.30pm at the Community Centre, Church Place, Pill, BS20 0AE
Following the exhibitions, the plans will go on display from:
Monday, November 27 – Between 9am and 5pm at 100 Temple Street, Bristol, BS1 6HT
Source:
Bristol Post It comes after an updated budget in March revealed the first phase of the project had trebled in cost from £58million to between £145 and £175million.
...the reopened line will provide a £264million boost to the local economy over the next decade... MetroWest Phase 1 will reduce journey times which will not erode over time.
The arithmetic would suggest that it is still a good idea. Can we drop