Portishead rail update
Date:
21/01/2016
Despite comments published to the contrary, North Somerset Council has confirmed that work will begin on the Portishead line in 2018 as previously stated, although the complexities of the construction work may see the opening of the line to rail services moving from May 2019 to around about the year end.
Progress on Metrowest phase 1 ^ which will provide improved services to Bath, Severn Beach and new services on the line to Portishead ^ will be officially reported to the Joint Transport Board next week.
Outline design work is progressing well and is on schedule for completion this April. This work has identified a number of engineering challenges which the team is working through before statutory consultation begins in June. An application for a Development Consent Order will then be made in November ^ this is required before any construction on the line can begin. It is expected to take up to 18 months for the secretary of state to grant planning consent, after which work on the line can begin.
The outcome of the consultation from last summer has also recently been published. A total of 599 people attended the four manned public exhibition events and 858 consultation responses have been received. A number of responses from statutory bodies (for example Historic England and utility companies) have also been submitted.
The level of support for the project is very high with 95% of responses either supporting entirely or mainly supporting the proposals. The report sets out in detail the level of support for the individual elements of the project and the areas of concern, which generally relate to localised impacts such as parking and traffic impacts and environmental impacts.
Officers from North Somerset Council and West of England colleagues are feeding the consultation responses into the outline engineering design and following any necessary modifications stage 2 of the consultation process is expected in June. This will provide an opportunity for people to make final comments on the proposals before the submission of the Development Consent Order planning application.
Cllr Elfan Ap Rees, North Somerset Council deputy leader who also holds the transport portfolio, said: "I am encouraged about the progress of the project, which we believe is the largest rail scheme in the country being locally funded. It is not a simple re-opening project but well worth waiting for.
"The new half-hourly service to Portishead will be far better than was ever available in the 1960s, so is not a like for like replacement of previous infrastructure and we need to make sure that the existing freight services to the port are not adversely affected. While the project is on track to begin construction in 2018 as planned, we need to co-ordinate the work with the improvements planned by Network Rail to deliver electrification and other enhancements in the Bristol area and as always on projects of this scale and complexity, timescales are kept under review and we continue to explore opportunities to accelerate delivery."
Work on the outline engineering design began last summer and is scheduled to be completed this spring. There are three distinct engineering design elements of MetroWest Phase 1:
^ The disused line Portishead to Pill
^ Upgrading the freight line and its connection onto the main line (Parson Street Junction), and
^ Other engineering enhancement works beyond the Portishead branch line.
The engineering design must provide sufficient railway line capacity to operate both the existing freight trains and our proposed passenger train service.
There have been major land use and demographic changes along the line, since scheduled passenger trains last operated in the 1960s. Royal Portbury Dock makes an important contribution to the local and regional economy and moving large volumes of freight by rail (that otherwise would go onto our roads), has economic and environmental benefits. While only a few freight trains operate on any typical day at the moment, allowances have to be made for one freight train per hour in each direction, in the engineering design. The proposed passenger train service includes operating considerably more passenger trains than operated on the line in the 1960s. The proposed half-hourly passenger train service (day time) will result in approximately 30 trains per day (Monday to Saturday) in each direction.
Providing sufficient line capacity for these freight train and passenger train presents some challenges. The four (single bore) tunnels through Avon Gorge mean the five kilometre section of track from below the Clifton Suspension Bridge to Ham Green will remain single track. This section of single track also has some environmental challenges due to the various national and European environmental designations.
So it will be necessary for the freight line speed to be increased and for the remaining sections of single track to be upgraded to double track, along with complete replacement of the signalling system. These requirements and constraints complicate the engineering design, which means the project is not about putting back the track and related infrastructure that existed in the 1960s; it's about re-building the disused line to modern engineering standards and upgrading/modernising the freight line.
Full details on the consultation can be found in the 'Report on
DCO▸ Stage 1 Consultation' at:
http://travelwest.info/projects/metrowest/metrowest-phase-1- See more at:
http://www.n-somerset.gov.uk/News/Pages/Portishead-rail-update.aspx#sthash.sojK4mr6.dpuf